Contractor signed up for early works at one of Queensland’s biggest battery projects

Published by

Australian renewable energy company Atmos Renewables has secured an important milestone in the development of its Teebar battery energy storage project (BESS), a proposed 400-megawatt (MW), four-hour big battery in Queensland.

The company says it has signed an Early Contractor Involvement (ECI) Agreement with South Australian energy construction company Enerven.

The ECI phase – the initial stage in a project’s development which introduces a contractor before the final design is complete – is expected to take approximately five months and will include site studies, detailed engineering design, management plans, and permitting support.

As it currently stands, the Teebar BESS will be located adjacent to Powerlink’s Teebar Creek substation in central Queensland, approximately 60 kilometres west of the township of Maryborough.

Construction is expected to begin in the third quarter of 2026, creating up to an estimated 200 jobs at peak construction.

Atmos Renewables has also promised to “place a strong emphasis” on working with local First Nations businesses, building regional employment pathways, and supporting local capability through various procurement and supply chain opportunities.

“Selecting Enerven as our early-stage BOP contractor strengthens our delivery confidence and our ability to achieve the project’s objectives and timeframes,” said Aideen McGuigan, development manager at Atmos Renewables.

“As this is a first development project in Queensland for both Enerven and Atmos, we look forward to creating long-lasting benefits and opportunities for local contractors and supporting the local supply chain so that the Teebar BESS delivers enduring value for the state and its communities.”

If you would like to join more than 28,000 others and get the latest clean energy news delivered straight to your inbox, for free, please click here to subscribe to our free daily newsletter.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Wholesale power prices plunge as renewables surge, batteries boom, and gas hits 23-year low

Wholesale electricity prices surge as wind displaces coal, batteries push out gas and home storage…

28 July 2026

Sunshine state sets new solar record – in the middle of winter

Queensland has set a new record for the share of solar power in its electricity…

27 July 2026

Electricity network tariffs are a dog’s breakfast – where to now for distributors?

With less need for networks to perform their traditional role, and the state of tariffs…

27 July 2026

Climate groups back push for data centres to BYO renewables, ahead of Friday ministers’ meeting

Australia's growing number of large-scale data centres must be powered by renewable energy, groups say,…

27 July 2026

Quinbrook seeks approval for large solar farms to help power Australia’s push into making silicon for PV

Quinbrook begins planning journey for the first of two solar projects worth up to 500…

27 July 2026

Wind project cut in half due to weak wind resource and after strong community opposition

Plans to develop a wind farm in Queensland’s Whitsunday region have been cut in half,…

27 July 2026