Storage

Construction starts on new big battery after landing “first of its kind” debt package in NSW

Published by

Equis Developments says it will start construction of a new big battery project in the New England region of NSW after landing a “first of its kind” debt finance package from Australian and international banks.

The 250 MW and 500 MWh Calala battery is to be built next to the Tamworth sub station in northern NSW, using Tesla megapack technology, and is being developed by energy infrastructure company Equis Australia.

One part of the battery – amounting to 100 MW and 200 MWh – has secured a long term off take agreement with SmartestEnergy, while the remainder will be a “merchant” facility, using Tesla software to trade on the open electricity market.

Equis, which is also building the 600 MW, 1,600 MWh Melbourne Renewable Energy Hub battery in Victoria – also using Tesla Megapack technology – says it is the first big battery in NSW to secure merchant debt financing in NSW.

Its $260 million of non-recourse senior debt financing was provided by Westpac, Society Generale and Sumitomo Mutsui Bank. Westpac was also involved the country’s first non recourse senior debt financing for a merchant facility, for the Bungama battery announced last month by Amp Energy.

The total cost of the Calala battery is $US328 million ($A522 million), a spokesperson said by email, which suggests it has not enjoyed some of the cost reductions cited by other battery projects in recent times.

Equis says it has been engaging with the Tamworth community – the battery will be located just over 5kms south east of the city – since 2022.

“Our experienced in-house planning and communications team are committed to thorough and transparent community engagement,” said Mahesh Reddy, the head of Equis Australia.

“This approach is reflected in our team’s ability to secure development approval for our projects at an average of 5 months which is significantly faster than the industry average.”

SmartestEnergy, a UK-based retailer that is wholly owned by Japanese industrial giant Marubeni, described it as a “watershed” moment for the company, as it is its first big battery contract and will support its growing retail business in Australia.

“This is a watershed moment for SmartestEnergy. To lead in the future energy market, you need firming assets like this. It’s no longer optional,” said Alex Uziallo , the head of origination at SmartestEnergy Australia.

See Renew Economy’s Big Battery Storage Map of Australia.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Chart of the Day: Farewell King Coal, long live King Solar (and wind and batteries)

In capacity-addition terms, fossil fuels are now just a thin orange strip at the bottom…

16 June 2026

Data centres could unblock renewables bottlenecks – if they don’t hit barriers of their own

Report says data centres could fix the demand shortage and tenor gap needed to get…

16 June 2026

Farmers welcome “nation-leading” guidelines for wind, solar and batteries – but warn they are not binding

Greater transparency between neighbours and better coordination across industry sectors are among a new set…

16 June 2026

Network tariffs: Imagine if the AEMC was in charge of selling milk

If the AEMC really thinks that we should pay for networks just like we pay…

16 June 2026

Photo of the Day: Australia should allow wind turbine blades to be trucked in convoy

Updated: In China, they deliver wind turbine blades in convoy to project sites. It must…

16 June 2026

Fortescue to lease electric haul trucks as part of land deal with traditional owners

A new land access agreement between Traditional Owners of the Pilbara region and iron ore…

16 June 2026