Construction begins on Nyngan, Australia’s largest solar PV plant

Published by

Construction of AGL Energy’s $300 million solar PV plant in central NSW is set to begin, with the head contractor, First Solar, going on-site on Tuesday.

The ARENA-backed Nyngan Solar Plant – with more than 1,350,000 PV modules expected to be installed on a 250 hectare site – will be the largest PV plant in Australia, and the largest of its kind in the Southern Hemisphere, once finished.

Construction is expected to take around 18 months to complete, with the 102MW plant slated to be fully operational by June 2015.

Nyngan Solar Plant had its inception in the federal government’s Solar Flagships program, a renewables scheme created under the first Rudd regime to foster the development of utility-scale solar projects.

After some years and a good deal of trouble securing the private financial backing necessary to gain access to the government funds, AGL managed to bridge the gap with a little help from the NSW Government ($64.9 million), the Education Infrastructure Fund($40 million), and the federal government’s Australian Renewable Energy Agency, or ARENA ($166.7 million).

Once completed, the Nyngan Solar Plant will produce enough electricity to power more than 33,000 average NSW homes and to reduce CO2 pollution by more than 203,000 tonnes every year.

AGL group general manager of merchant energy, Anthony Fowler, said the project, which began more than four years ago, would provide significant flow on benefits to the Nyngan region, including 300 direct construction jobs created to support the plant’s construction, and with the majority of workers expected to be housed in an accommodation camp being built in Nyngan.

The Nyngan plant will be complemented by AGL’s second solar plant at Broken Hill, due to commence construction in mid-2014, with an expected completion date of November 2015.

Together the two solar plants will cover an area equivalent to Sydney’s CBD and North Sydney with PV modules, and will deliver a total capacity of 155MW of energy for NSW.

First Solar will provide engineering, procurement and construction services for the Nyngan and Broken Hill Solar Plant projects, using its advanced thin-film PV modules. First Solar will also operate and maintain both projects for AGL for five years after commercial operation starts.

“Breaking ground at the Nyngan solar project is a significant milestone for the advancement of Australia’s utility-scale solar industry,” said Jack Curtis, First Solar’s Vice President of Business Development for Asia Pacific.

“Each project that First Solar constructs builds acceptance of and confidence in utility-scale solar as an effective source of power generation in Australia. As the Nyngan project develops, we look forward to seeing its impact, not only in generating important local job opportunities, but also in strengthening the solar industry’s position within Australia’s energy mix.”

ARENA CEO Ivor Frischknecht said the project would generate valuable know-how in deploying large-scale solar PV as well as help support job creation in regional NSW.

“The transfer of skills and experience to the local labour market will provide a boost to the local community and beyond as well as benefit the solar industry and the Australian economy,” Frischknecht said.

“AGL has already learned valuable lessons during the planning stages of the project, which ARENA has shared with the industry in a guide to gaining regulatory approvals, he said. “Sharing knowledge helps build investor confidence, reduce risk and costs on future projects and paves the way for more solar energy plants to be built across the country.”

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024