Construction begins on four hour Kwinana battery to soak up rooftop solar

Published by

Construction has already begun on the second phase of the Western Australian Kwinana Battery, just weeks after the project gained planning approval.

The government, through its state-owned utility Synergy, is building the 200MW, four hour (800MWh) battery next to the 100MW, two hour (200MWh) first stage of the Kwinana battery that was only recently completed.

The new batteries are part of an accelerated plan by WA authorities to address the growing issues around the “solar duck” curve in the world’s biggest isolated grid, and are designed specifically to soak up rooftop solar produced in the middle of the day and send it back out to the grid in the evening peaks.

Another two big batteries are also planned to help address the same issue – a 219MW, four hour (877MWh) battery to be built by Neoen at Collie, the first stage of a potential 1GW, 4GWh battery at the same site.

Synergy has also announced a 500MW, 2000MWh battery planned by Synergy in Collie – and will submit a planning application later this year – and a second  500MW, 2000MWh battery in the region as the state prepares to shut down the last of the state-owned coal generators by the end of the decade.

“WA is unique in its energy security because we are not connected to other networks,” energy minister Bill Johnston said in a statement.

“Our energy management sets us apart from the rest of Australia. By investing in renewable energy and battery storage solutions, this government is safe-guarding the long-term resilience and flexibility of our electricity network.”

Built on the site of the former coal-fired Kwinana Power Station, the first stage of the Kwinana Battery was switched on in June. It was built by NHOA Energy, using CATL technology.

This second grid-scale battery energy storage system is backed by $625 million from the Western Australian state government and will consist of 288 shipping container-sized battery modules and 72 inverter units.

The project is expected to be completed by late 2024, during which time more than 160 jobs will be created for construction.

“My government is getting on with delivering our plan for cleaner, reliable and affordable energy for Western Australia,” said Roger Cook, premier of Western Australia.

“The start of construction for WA’s second grid-scale battery energy storage system is an important milestone in WA’s energy transformation. WA is a leader in the uptake of residential solar energy, and these big batteries help to ensure our energy system remains reliable as we transition away from coal-fired power.

“It is particularly fitting that we’re building the infrastructure of future at the site of the old Kwinana Power Station – keeping the Kwinana industrial strip front and centre as our energy system transitions to a new future.”

The former Kwinana Power Station was originally commissioned in 1970 and consisted of a mixture of turbines driven by steam from boilers fired by coal, natural gas, or fuel oil, as well as a 20MW gas turbine.

See RenewEconomy’s Big Battery Storage Map of Australia

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024