Renewables

Concrete pours nearly complete, first blades due soon at state’s only wind project under construction

Published by

Australia’s largest renewable energy developer Squadron Energy is officially a third of the way through building the 414-megawatt (MW) Uungula wind farm, with nearly all concrete foundations poured and regular weekly delivery of components.

Renewable energy developer, operator, and owner Squadron Energy, wholly owned by the Andrew Forrest’s investment vehicle Tattarang, announced on its LinkedIn account at the end of last week that nearly all foundations at the 414 MW Uungula wind farm had been poured.

The milestone comes less than a fortnight after Squadron Energy also revealed that it had begun pre-installation of the site’s 69 wind turbines and the arrival of transformers for the project’s electrical infrastructure.

According to Squadron Energy, more than 100 turbine components have already been delivered and up to 26 deliveries are taking place each week.

Delivery of the turbine blades is also expected to begin soon.

By last Friday, eight turbine towers had been preinstalled – consisting of the installation of three mid tower sections atop the base section which is fitted into the turbine tower’s concrete foundation.

“This phase of construction represents strong momentum for Uungula Wind Farm, with teams now actively and safely assembling lower sections of each turbine tower,” said Sanjay Goel, Uungula wind farm project director. 

“Seeing the first sections of the tower going up brings us a step closer to delivering a project that will generate enough clean energy to power more than 200,000 homes and businesses.” 

The Uungula is the only wind farm currently under construction in New South Wales, home to Australia’s biggest fleet of coal-fired power plants. With the state’s ageing coal fleet due to retire over the coming decade, the NSW government is scrambling to secure enough new renewable energy capacity to fill the looming shortfall.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, you can click here to subscribe to our free daily newsletter.

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

“Only so much you can do” with hydrogen and batteries: Jet fuel made from cooking oil to be used at Australian airport

Jet fuel made from used cooking oil will be used at an Australian airport for…

6 July 2026

Planning meeting over solar and battery project cancelled after none of 133 objectors bothers to show up

A public meeting to hear objections to a large solar and battery project in New…

6 July 2026

Australia’s newest international airport to be powered by 100 pct renewable electricity

Australia's newest international airport will be powered by 100 pct renewables, thanks to a large…

6 July 2026

Huge solar and battery project nears construction start after feds provide final green light

A massive NSW solar-battery project backed by federal and state support and in one of…

6 July 2026

Snowy warns of “odour and plume” as it commissions diesel generators at delayed and over-budget peaking plant

Snowy Hydro warns residents of "odour and plume" as it commissions diesel component of its…

6 July 2026

Grid access rules to be changed, but won’t penalise “advanced” projects that are ready to build

Advanced projects that are ready to build may be exempt from new changes to grid…

6 July 2026