Collinsville 42.5MW solar farm underway as site works begin

Published by

Ratch Australia’s long-planned bid to build a solar farm on the same site that once hosted a 180MW coal-fired power generation facility have come to fruition, with the commencement this week of works on the $100 million, 42.5MW Collinsville PV project in Queensland’s Whitsunday Region.

Project developer Ratch said on Wednesday that it had broken ground on the solar farm, after the project’s engineering, procurement and construction contractor, UGL Limited, assumed formal control of the site late last month.

Ratch appointed contractors to the job in May, after the the project reached financial close with the help of a $60 million commitment from the Clean Energy Finance Corp. And in March, Ratch secured a power purchase agreement with Alinta Energy to buy the PV farm’s electricity and large-scale generation certificates until the end of 2030.

Ratch said civil construction, earthworks and other preparatory activities were at the top of the solar project’s works schedule, ahead of delivery of the first of 163,000 solar photovoltaic panels in September.

Several businesses from the Whitsunday’s region are involved in the construction activities including Collinsville’s Beauchamp Excavating, Proserpine’s Pyro Dynamics, and Bowen’s S&W Crane Hire which was busy delivering site facilities this week. Bowen-based Australian Indigenous Security Services will provide security services at the site.

“Ratch has found the best project outcomes are delivered when as many local people and businesses are involved as possible,” construction manager Glenn Rice said in comments on Wednesday. “The region is well known for the depth of industrial capabilities and skills plus an understanding of how to deal with local climate conditions is a huge asset.

“We are excited to get works underway after such a long planning and development process. We’re confident we have the right team in place to deliver a world class solar farm, and we are on track to be operating by this time next year,” he said.

Ratch owns and operates several renewable energy projects in Australia and is also managing the construction of the 180MW Mount Emerald Wind Farm near Mareeba which is due for completion in September next year.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: The urgent grid upgrades WA needs to quit coal and power green industry

Western Australia risks losing jobs and investment in its two most prized industrial regions without…

10 September 2026

Households tipped to spend $85 billion on energy upgrades, but renters and young Australians could miss out

Spending on home energy upgrades such as insulation and solar panels is on the rise…

9 September 2026

“Overlooked” challenge: Data centre boom could lift e-waste load 10-fold, increase “forever chemical” risks

Environmental authorities will be faced with a wave of new e-waste as data centre industry…

9 September 2026

“Australian first” grid-connected sodium-sulfur battery powers up, just as supplier halts production

Australia’s first grid-connected, industrial-scale sodium-sulfur battery will support materials processing plant and demonstrate novel long-duration…

9 September 2026

Massive and unprecedented injection of power as Super Battery tests its full shock-absorber capacity

Australia's most powerful battery injects a massive and unprecedented amount of power into the grid…

9 September 2026

Too old, can’t dance: New numbers show Yallourn is ready to retire

Report says Yallourn is old and clunky and ready to retire, and replacing it gas…

9 September 2026