Collapse of contractor puts more question marks over giant Snowy 2.0 project

Published by

The giant Snowy 2.0 pumped hydro project – already steeped in controversy and facing significant cost overruns and delays – is facing further question marks over its future after the collapse of the one of its main contractors.

Clough Engineering has been placed in administration after its partner in the Snowy 2.0 contract, the Italian based We Build, pulled out of the deal to buy the company and inject some much needed cash.

The two companies announced the proposed purchase in November after Clough’s owners, the South Africa-based Murray & Roberts, had warned of delays, cost over-runs and the lack of a working capital facility threatened to impede its operations.

“It’s ludicrous,” the company’s chief financial officer said in September of the lack of a working capital facility, which would help bridge the gap between payments for supplies, and from its client, the federal government owned Snowy Hydro.

The deal with We Build involved an interim injection of $30 million in cash to enable Clough to continue operations, and the purchase of the company for a peppercorn sum of $500,000 and the forgiveness of a $350 million intracompany loan.

But after a close look at the books, We Build pulled out. “There is no reasonable prospect of that acquisition proceeding through to a successful completion,” it said in a statement.

“The parties have therefore unconditionally agreed to terminate the sale and purchase agreement with immediate effect.”

Murray & Roberts said late Monday it had no choice but to place Clough into administration given its urgent working capital needs.

A Deloitte Australia corporate rescue team  comprising Sal Algeri, Jason Tracy, Glen Kanevsky and David Orr have been appointed administrators and will pursue options for sale, restructure or recapitalisation.

It is not immediately clear how this will impact the Snowy 2.0 project, which is running over its already inflated budget of $5 billion, and facing delays of up to 18 months – all due to a combined impact of Covid19 delays, cost rises and supply chain impacts.

Murray & Roberts warned in late October that it faced being put into voluntary administration itself because it has no ability to repay the inter-company loan, inherited from the buyout of Clough minority shareholders in 2013.

It also revealed at the time that Clough was facing deeper losses because “of a deterioration of estimated project margins.”

The Snowy 2.0 has been widely criticised for being a “vanity” project and over its economic and environment credentials, and its impact on the energy market. It has caused many smaller projects not to be built, and  further delays could cause problems as the exit of coal continues apace.

Federal energy minister Chris Bowen in June announced that the project was running up to 18 months behind schedule, amid reports that it could be up to $2 billion over budget due to delays, logistics problems and supply constraints and costs.

Snowy Hydro in November finally confirmed that the budget for the Snowy 2.0 project had blown out to just under $6 billion and is running around 12 months behind schedule. Snowy executives still pocketed millions in bonuses, including for meeting cost and performance targets on the controversial project.

 

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Buyer Beware: Carbon credit platforms repeating ills of the past

Claims and promises of carbon offset schemes are falling deep into the category of being…

23 January 2026

“Total transformation of the Australian summer:” Climate change made January heatwaves five times more likely

Australia has just experienced its worst heatwave in six years but it's set to become…

23 January 2026

Shared solar: Labor’s “free power” plan to have daily cap to stop abuse by EV and home battery owners

There will be daily cap on the federal government's Shared Solar free power offer, to…

23 January 2026

“Reduced appetite for solar:” Giant hybrid project slashes PV component by half as it seeks green tick

Developer of what was once hailed as the biggest solar hybrid project cuts PV component…

23 January 2026

“Tallest, Mightiest and Widest:” Fortescue’s unique wind tech sees 30 pct cost savings over traditional towers

Fortescue wind technology company says its turbines will be the "tallest, mightiest and the widest,"…

23 January 2026

Biggest battery on standby as rooftop PV sets stunning new records, meeting 117 pct of state demand

Rooftop solar reaches remarkable 117 pct of state demand in Australia's most advanced renewable state,…

23 January 2026