Coal

Coal plants must give 3 years’ notice of closure, under new market rule

Published by

Owners of Australia’s ageing coal-fired power plants – and other generators for that matter – will have to give at least three years’ notice of plans to close down the generators, according to a new rule completed by the Australian Energy Market Commission.

The AEMC said on Thursday that the rule change – based on one of the recommendations from the energy market review by Australia’s chief scientist, Alan Finkel – would promote reliability in the National Electricity Market. It will come into effect from July next year.

“It does so by creating a framework that requires generators to provide AEMO with the closure year for all their scheduled and semi-scheduled generating units,” the AEMC said in its final determination summary on Thursday.

“It also requires them to provide AEMO at least three years’ notice of their intention to permanently close a generating unit by notifying the date they wish to terminate the classification of the generating unit,” the paper says.

“The provision of this information to the market will assist in managing the market impacts of the retirement of the existing coal-fired generators as they reach the end of their economic lives.”

The new rule comes in the wake of last year’s closure of the Hazelwood coal-fired generator in Victoria’s Latrobe Valley, which was unceremoniously shuttered by its French owner, Engie, for commercial reasons.

And it anticipates the imminent and inevitable closure of the remainder of Australia’s ageing coal fleet, led by AGL Energy’s Liddell plant in New South Wales.

As it happens, AGL has provided a good seven years’ notice of its plans to close Liddell at the end of its life in 2022, along with detailed plans to replace its capacity with a mixture of wind, solar, battery storage, demand management, a new generator and an upgrade of the Bayswater coal fired power station.

These plans have met with considerable resistance from the federal Coalition government, however, which wants Liddell kept running for a further five years, despite its decreasing reliability.

The AEMC rule does permit a generator to provide its first notice of closure with less than three years notice, but only in circumstances where an exemption has been granted by the Australian Energy Regulator.

It also requires an amended notice of closure to provide no less than three years notice from the date the amended notice is provided, unless the closure date extends a previous closure date, or an exemption has been granted by the AER.

In its “rationale” of the new rule, which was finessed by the Energy Security Board’s Kerry Schott, based on the Finkel recommendation, the AEMC said its main purpose was to protect consumers from avoidable electricity price rises.

“Recent experience shows that sudden and unexpected retirement of large generators can cause undesirable consequences in the market, such as a material increase in wholesale prices,” the AEMC said.

“Provided with sufficient notice, the market has time to respond, minimising the likelihood of any price shocks.”

Reliability of supply was also part of the Commission’s consideration, although it admitted an outcome of insufficient generation to meet demand was much less likely to occur, particularly with due notice.

“These concerns [of security of supply] may not eventuate if information on plant retirement is provided to the market in sufficient time for participants to respond,” it said.

“This time allows market participants to factor this information into their investment, operational and retirement decisions, potentially changing their decisions.

“For example, another generator may decide to stay open longer or bring forward its plans to invest in new generation.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

AGL-backed offshore wind farm pulls out of contention for Gippsland zone

AGL Energy has pulled its Gippsland Skies offshore wind project, citing challenging economics and a…

5 December 2025

Giant 50 kWh systems eat up Cheaper Home Batteries budget, as changes to rebate look likely

Australia's home battery rebate being eaten up by systems sized at 50 kWh and above,…

5 December 2025

How to break Australia’s dependence on spinning machines, and run the grid with fossil engines off

The assumption that big spinning machines are needed to keep the lights on could delay…

5 December 2025

Sulfur battery innovator clears key milestone to commercialisation – and to compete with li-ion

Australia-originated energy storage innovator clears major new milestone for its sulfur battery technology that brings…

5 December 2025

Energy Insiders Podcast: No spin needed for renewable gold rush

Energy systems expert Bruce Miller explains why spinning machines won't be needed in future grid,…

5 December 2025

Offshore wind farms could be used as charging hubs for electric and hybrid ships

Two Danish companies are exploring the possibility of integrating offshore wind with marine electrification –…

5 December 2025