Renewables

Clean Energy Regulator confirms the RET is met

Published by

Australia’s Clean Energy Regulator has confirmed that the federal government’s 2020 Renewable Energy Target is as good as met, by wind and solar projects either already built or in the works.

In a market update released on Friday, the CER said there was now 6553MW of capacity from new renewable energy projects under construction or already built – considerably more than the 6400MW of capacity required to meet the 2020 RET of 33,000GWh.

A further 1454MW of projects, it said, were likely to be fully financed and under construction this calendar year, via power purchase agreements.

“We expect the 2020 Renewable Energy Target will be exceeded at current build levels,” the Regulator says in the report.

“We remain confident the market will continue to operate with a healthy working surplus of around 5 million LGCs in 2018 and 2019. The surplus should start to increase again from 2020.”

The Regulator also noted that if the spot LGC price remained high, electricity retailers may “time shift demand,” either by carrying forward less than 10 per cent of their liability to later years, or by paying the shortfall charge.

This means that retailers that have not bought enough LGCs to meet their obligation will “pay the shortfall charge” now and buy LGCs later.

According to the rules of the scheme, however, these companies have three years grace to pay, allowing them to buy when prices fall – as ERM Power did last year.

CER executive general manager Mark Williamson said the build-out of renewables in Australia, including the booming commercial and industrial solar market, was exceeding expectations.

“We do think everybody is underestimating the pace of (renewable energy development),” Williamson told Australian Energy Week in Melbourne on Friday.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

A massive 244-tonne transformer completes 2,165 km road trip to Australia’s largest solar project

A massive 244-tonne transformer has completed a 2,165 km road trip to the site of…

17 October 2026

Energy Insiders: Grid scale sodium batteries are on their way

The battery industry is about to witness another change in chemistry and technology. Valo Energy…

16 October 2026

“Just a fantasy:” Energy minister slams Opposition gas and nuclear ideas, vows to hold the line on renewables

Energy minister says imminent closure of coal is "indisputable," and "ideology-driven" policies to scrap transmission…

16 October 2026

Supplier to Australia’s biggest battery expects to announce first sodium-ion battery project soon

The supplier to the biggest battery currently being built in Australia expects to announce its…

16 October 2026

Wind projects will need help “for a while”, says new green bank boss in shift of funding priorities

The federal government green bank has dusted off an old mandate, but has not ruled…

16 October 2026

Anti-renewables groups still spending big on Meta – and met with near silence by green energy industry

Fossil fuel interests spent $1.2 million on Meta ads in the last three months, a…

16 October 2026