Chevron concedes CCS failures at Gorgon, seeks deal with WA regulators

Published by

The operator of Australia’s only commercial-scale carbon capture and storage project has conceded the project has failed to meet its targets, and is now seeking a deal with Western Australian regulators on how to make up for millions of tonnes of carbon dioxide it failed to store.

On Monday, Chevron announced that it had finally succeeded in sequestering five million tonnes of carbon dioxide at its carbon capture and storage facility at the company’s Gorgon LNG plant.

While Chevron celebrated this as a “significant milestone” for the project, it falls well short of what was promised to regulators when the massive $70 billion LNG project was first announced in 2009.

The storage project is supposed to be capable of storing at least 80 per cent of the carbon dioxide produced by the Gorgon LNG facility, or around 4 million tonnes a year. The storage was one of the key conditions for state government approval.

Chevron is understood to have spent more than $3 billion building the carbon capture facility, but it took several years after the start of gas production for the Gorgon CCS project even to begin operation due to delays and technical difficulties. The first CO2 was injected into an undersea deposit in 2019.

The project encountered further difficulties after its commissioning, with sand clogging parts of the storage system and dramatically reducing the amount of carbon dioxide it was able to inject underground.

It is understood regulators may ask Chevron to offset the emissions it failed to store by purchasing offsets from either local or international carbon markets. If Chevron is made to buy Australian Carbon Credit Units, which currently trade at above $20 per tonne, the cost to the company could easily exceed $200 million.

In its Monday announcement, Chevron conceded that it had missed its targets and was now in active discussions with the Western Australian government around how it could make good its failure to deliver on the expected storage of carbon dioxide.

“Chevron is working with the WA regulator on making up the shortfall and will report publicly on that later in the year,” Chevron Australia managing director Mark Hatfield said. “Like any pioneering endeavour, it takes time to optimise a new system to ensure it performs reliably over 40-plus years of operation.

“The road hasn’t always been smooth, but the challenges we’ve faced – and overcome – make it easier for those who aspire to reduce their emissions through CCS.”

The Gorgon project is Australia’s only commercial-scale carbon capture and storage project and despite its delays and operational problems, the company said that CCS remains a “proven technology.”

“CCS is a proven technology which experts agree is critical to achieving a lower carbon future while ensuring access to affordable and reliable energy for billions around the world who rely on it,” Hatfield added.

The Federal government contributed $60 million towards the cost of Chevron’s Carbon Dioxide Injection Project at Gorgon under the Low Emissions Technology Demonstration Fund and is expected to reduce emissions at the facility by 100 million tonnes over the project’s 40-year life.

The Morrison government is relying heavily on CCS technologies to deliver reductions in greenhouse gas emissions – selecting it as a core technology under its Technology Investment Roadmap and using it as justification to pour significant amounts of public funds into its development.

But the Climate Council said the Gorgon failure is another example of CCS failing to live up to its promise, and said it did not provide a viable pathway to decarbonising the energy system.

“This admission from Chevron highlights once again that carbon capture and storage (CCS) in the fossil fuel sector is an expensive failure,” Climate Council senior researcher Tim Baxter said.

“Over the past decade, the costs of renewable energy like wind and solar have plummeted. Over the same period, CCS has remained extremely expensive. There are still no projects operating anywhere in the world that have delivered CCS on time, on budget, or in the quantities promised.”

“CCS is simply an attempt to prolong the life of polluting fossil fuels which are driving climate change. We need to transition away from burning coal, oil and gas and instead power our economy with renewables and storage,” Baxter added.

Michael Mazengarb is a Sydney-based reporter with RenewEconomy, writing on climate change, clean energy, electric vehicles and politics. Before joining RenewEconomy, Michael worked in climate and energy policy for more than a decade.
Michael Mazengarb

Michael Mazengarb is a Sydney-based reporter with RenewEconomy, writing on climate change, clean energy, electric vehicles and politics. Before joining RenewEconomy, Michael worked in climate and energy policy for more than a decade.

Recent Posts

Buildings as batteries: How basic demand response could shift 12GW of peak demand, save billions

New study finds that if one-third of commercial buildings shifted consumption from late afternoon to…

24 April 2024

Australian pioneer in shared rooftop solar scores big from Biden billions

Australian company specialising in shared solar is a big winner from the US government’s $7bn…

24 April 2024

NSW to open bids for access to first two renewable zones, in race to plug in new wind, solar and batteries

Applications open for a spot on the grid in the Central West Orana REZ, while…

24 April 2024

Fortescue says green hydrogen target still on track, but Australia projects stalled by power prices

Fortescue boss says China's roll out of wind and solar "blew his mind", and the…

24 April 2024

Alinta lands powerful new partner for offshore wind project – and identifies a site near smelter

New Japanese renewables outfit signs on to plan to power Portland Aluminium Smelter with a…

24 April 2024

Nine projects in “hard to abate” sectors share $330m of federal funds to slash emissions

Companies across cement, alumina, mining, metals and food processing sectors share in $330 million in…

23 April 2024