Cheaper renewables force closure of NZ’s last coal-fired power units

Published by

Utility-scale coal-fired power generation will soon be a thing of the past in New Zealand, after local gentailer Genesis Energy said it would close the last two coal-burning units at its coal and gas Huntly power station in Waikato, on the North Island, due to falling demand and lower-cost renewables.

Stuff.co.nz reports that the 953MW plant’s remaining two coal-burning units – the two others have already been retired – will be shut down in 2018, after running “at the margin of the market” for a number of years, according to Genesis.

Indeed, the gentailer said it had been on track to retire the four coal/gas fired “Rankine” units – which were commissioned in the early 1908s, when they were seen as less expensive than building extra hydropower – since 2009.

“The development of lower cost renewable generation, principally wind and geothermal, investment in the HVDC link (the Cook Strait cable), and relatively flat growth in consumer and industrial demand for electricity have combined to reinforce the decision to retire the remaining Rankine units, which will deliver further operational efficiencies to Genesis Energy,” said Genesis chief executive Albert Brantley.

Closure of the coal units – which Genesis said would mark the end of large scale coal-fired generation in New Zealand – is expected to produce operational and capital cost savings for the company of approximately $20 to $25 million a year.

It will also cut the Huntly power station’s capacity by more than half (around 500MW), limiting it to the two existing gas-fuelled units – the high efficiency 400MW “Unit 5”, and the smaller 50MW open cycle “Unit 6″ – and shifting NZ’s electricity market further into renewables.

While this has concerned some analysts, who warned that future dry spells could lead to drastically reduced hydro capacity and, thus, to power shortages, Genesis said New Zealand’s power system was now better able to cope with dry years, even without coal.

“While there was a dry year in 2007/08 the extra generation required from Huntly came from Unit 5, not the Rankine coal fired units – their output decreased in this year from the previous year and kept on decreasing year on year to now,” a Genesis spokesman said.

The shuttering of the coal plants has been welcomed by NZ green groups, and – in stark contrast to Australian PM, Tony Abbott, and his response to the likely abandonment of the proposed Adani mega-coal mine project in Queensland – even by NZ Prime Minister John Key, who is reportedly “unsurprised” by the closures.

“I mean, in a lot of ways it’s unsurprising because the costs actually for Genesis, with the ETS and the likes, means that probably in the long-term coalfire power plants aren’t the most sensible plants to have,” Key said. “From New Zealand’s emissions perspective, this is actually probably a good thing.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Licences sought for Australia’s biggest wind, solar and battery hybrid to power giant gold mine

Licences sought for what will be the biggest wind, solar and battery hybrid of its…

11 August 2026

Pakistan’s citizen-led solar rush: Where panels power education and health – and are gifted in dowries

In Pakistan, a country with 250 million people and a GDP per capita of about…

11 August 2026

Plans for one of Australia’s biggest new gas plants sail through EPBC queue in just over two weeks

As wind generation proposals get stuck in EPBC limbo, plans for what could be the…

11 August 2026

Last turbine goes up as major wind farm completes expansion to become biggest in state

The last of 30 additional turbines have been added to existing wind farm, making it…

11 August 2026

Investor behind Amber Electric hits $10 million under management, milestone for new fund

Sydney based early-stage climate technology investor reaches $10 million under management and secures first close…

11 August 2026

SwitchedOn podcast: Biggest barrier to electrifying apartments? Knowing what’s possible

Strata manager Ash Sayers explains why getting the right advice early can turn apartment electrification…

11 August 2026