Press Releases

Cattle Hill Wind Farm substation energised

Published by

PRESS RELEASE

The substation and transmission line to link to the Cattle Hill Wind Farm to the transmission network has been completed and energised by TasNetworks.

Goldwind Australia Managing Director, John Titchen, said the substation’s completion is a major milestone for the project.

“Goldwind is pleased to be partnering with TasNetworks to achieve successful energisation of the substation for the Cattle Hill Wind Farm project. We have found the TasNetworks team to be very professional and capable.” said John.

“The commissioning and energisation of the substation is a key milestone in the project and has been made possible through a great team effort from everyone involved.” said TasNetworks CEO, Lance Balcombe.

“In addition to the construction of the substation on the wind farm site, approximately 130 metres of new transmission line has been built to connect the project to the existing transmission network and approximately three kilometres of existing transmission lines has been reconfigured to accommodate the future power output from the project.

“Construction of the project is progressing on many work fronts, six Goldwind turbines have now been installed and commissioning of turbines will commence shortly.

“Goldwind and Power China Resources Group appreciate the significant project progress, reflecting a team effort by many major project partners and approximately 150 staff currently working on site. Construction of the wind farm is planned for completion by the end of 2019” commented John.

Once the turbines are commissioned and generating power later this year, power will be fed via transmission line to the Waddamana substation and then into the state-wide transmission network. Once operational, Cattle Hill Wind Farm will produce enough clean energy to power approximately 63,500 Tasmanian homes.

Share
Published by

Recent Posts

Offshore hydrogen “energy islands” could save Germany €4 billion per year – report

Germany can achieve annual savings of up to €4.3 billion ($A6.4 billion) by establishing offshore…

2 October 2024

Coal generator switches off to to make room for solar in significant boost to renewable switch

The owner of one of Australia's biggest coal generators has shut down one of its…

1 October 2024

Battery hybrids favoured as wind and solar shortlisted projects make final bids in biggest ever tender

Final bids for the biggest tender for wind and solar capacity closed last week, and…

1 October 2024

St Baker battery giga factory starts commercial production in the Philippines

The StB Giga Factory has started making the equivalent of about 30,000 lithium iron phosphate…

1 October 2024

Nature, noise, rehab: Queensland tightens wind farm planning rules in renewables regulation overhaul

Wind farms proposed for development in Queensland will have to meet a number of new…

1 October 2024

Renewable records tumble for second day in a row, pushing fossil fuels to new lows

The instantaneous share of renewables in Australia's main grid reaches new highs for second day…

1 October 2024