“Catastrophic missile:” Report blames coal power plant explosion on safety breaches

Published by

A coal-fired power plant explosion described as a “catastrophic missile event” and one of the state’s greatest scandals could have been avoided, a long-awaited report has found.

Forensic engineer Sean Brady’s draft independent report on the 2021 Callide Power Station’s C4 unit incident in central Queensland that left almost half a million customers without power was released on Tuesday.

The damning findings into the explosion near Biloela prompted the government to appoint advisors to the board of the Callide C plant’s state-owned operators CS Energy.

A review of Queensland’s publicly owned energy businesses will also be conducted in the fallout over the draft report.

Three years after the incident, the draft report finally details what led to the “catastrophic failure”. 

It found while engineers were connecting a new battery system, there was a loss of power in the unit and no back-up system was in place following damage from an earlier incident.

The loss of power happened within two seconds, leaving the unit unable to operate normally, shut down safely or disconnect from the grid.

It ensured the turbine motor kept spinning, leading to a “catastrophic” failure of the plant.

Pieces of metal, weighing nearly half a tonne, blasted out of the turbine in what was labelled a “missile event”.

Dr Brady found CS Energy’s oversight in understanding and addressing the risks of not completing the upgrade to the redundancy battery chargers exacerbated the incident.

“If it had been operable … the turbine missile event would likely have been avoided, but the unit would still have sustained significant damage,” the report said.

CS Energy’s failure to comprehensively understand the issues with its systems led to it being unable to anticipate or prevent the incident.

“The failure to understand and assess risk, and to not effectively apply sound management of change processes in relation to the engineering factors that led to the catastrophic failure, suggests these were not isolated incidents, but rather a symptom of an organisation’s failure to value and implement effective process safety practices,” the report said.

There was no evidence that mechanical or metallurgical factors contributed to the explosion.

Premier Steven Miles has appointed special advisors to CS Energy’s board, among a number of measures that coincided with the report’s release.

“It’s timely now that we have this draft report to consider what further actions the government should take to ensure that nothing like this ever happens again,” he told reporters on Tuesday.

The review of publicly-owned energy businesses would be carried out before next year’s budget.

Mr Miles said the government would take public ownership of 100 per cent of the Callide C station from a private joint venture partner.

The government said further action may be taken when the final report was handed down.

Opposition Leader David Crisafulli described the Callide incident as one of Queensland’s greatest scandals.

“What has happened at Callide was avoidable. It’s completely and utterly disgraceful and it’s unforgivable,” he said.

The station’s Callide C3 generator has been back online since April.

The remaining turbine – Callide C4 – will make a staged return to service on June 30 before returning to full capacity on July 31.

AAP

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024