Carnegie installs second CETO 5 unit at WA wave energy project

Published by

Western Australian wave energy developer Carnegie Wave Energy has installed the second of its home-grown CETO 5 power generation units in waters south of Perth, where it has been operating successfully for over a week.

The ASX-listed company said on Tuesday that the unit was installed in one day at its Perth Wave Energy Project site off Garden Island, where it is operating alongside the first CETO 5 unit, installed in November last year.

The second CETO 5 unit being installed off Garden Island, WA
The second CETO 5 unit being installed off Garden Island, WA

Last week, Carnegie Wave completed its onshore power plant for the Perth Project, which when operating will become the first commercial-scale grid connected wave energy and desalinated water project.

As reported last week, the completion of the onshore plant triggered a payment to Carnegie of $54,444 from the WA government under its LEED Grant.

Carnegie also submitted a payment claim worth $316,785 for the completion of the milestone to the federal government granted under its ARENA Emerging Renewables Program.

Both installed CETO units are generating electricity against a load bank onshore, awaiting final approval from Western Power to transfer electricity to the grid at HMAS Stirling.

The third and final CETO 5 unit has been moved to the Australian Maritime Complex (AMC) in Henderson for final fit out ahead of its installation, which is expected to take place in around a month.

The demonstration project’s key objectives are to demonstrate the viability of the CETO technology and learn from the experience of deploying and operating multiple CETO units and the complete CETO system.

CETO Units 1 and 2 [circled]
CETO Units 1 and 2 [circled]It is also the only wave project to consist of more than one wave unit connected together and the only wave project to produce both power and freshwater.

“The integration of multiple wave energy convertors is critical to demonstrating the principles of future CETO wave farms,” said Carnegie managing director Michael Ottaviano.

“With the recent completion of onshore plant and grid connection works, we are eagerly anticipating the world-first milestone of feeding electricity into the grid at HMAS Stirling.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

“Wandering towards dystopia”: CSIRO scientists want open discussion of climate impacts before it’s too late

Senior CSIRO scientists discussed how to have an "open conversation" about the rising threats from…

20 October 2026

Oil giant’s renewables arm co-launches equal biggest solar farm in Aotearoa NZ

New 150 MW solar farm joins the NZ grid on the South Island, matching Aotearoa's…

20 October 2026

Pacific island needs “radical adaptation” to survive climate change, as leader calls out “brutal” COP commentary

Pacific leader turned activist says his island nation urgently needs to start "radical adaptation measures"…

20 October 2026

Laser tech could slash grid penalties for wind farms, because their forecasts are less wrong at the right times

A study tested two wind forecast models and found that more accurate one does not…

20 October 2026

Australia’s biggest wind projects stall as owners pass the hat around for billions of dollars in debt and equity

Australia's biggest wind projects have mostly locked in approvals and contracts, but are still shaking…

20 October 2026

Australian consumers are getting hit twice by diesel inflation, and it’s not likely to improve any time soon

New analysis says Australia's dependence on imported diesel means some households are getting hit twice…

20 October 2026