Emissions, logistics and pure economics – combined or individually – pose strong arguments against the Barossa gas project in the Timor Sea.

Producer Santos, in proposing carbon capture and storage to reduce the project’s climate impact, has added an impractical Band-aid solution to a haemorrhaging issue.

The LNG project looks like an emissions factory with an LNG by-product.

From offshore wells to initial processing on a floating production storage and offloading (FPSO) vessel, piping 300km to Darwin and onshore processing and conversion to LNG at the Darwin plant, CO2 emissions exceed the LNG production.

Add extra compression and piping and pumping of the proposed captured CO2 into the near-depleted Bayu-Undan gas field, and the project also looks even more economically and technologically impractical.

Barossa gas has an extremely high carbon dioxide content – about twice that of the next highest gas currently being converted to LNG in Australia. It is also much higher again than the gas feeding LNG plants in competitor LNG exporting countries.

Last month, Santos announced it would assess carbon capture and storage in depleted gas reservoirs at Bayu-Undan, 500km west of Darwin, to reduce emissions from the Barossa project.

The average emissions intensity of Australian-made LNG is approximately 0.70 tonne of CO2 per tonne of LNG produced. LNG from the Barossa project would have an emissions intensity more than double that amount before it is transported and burnt in North Asian markets.

The majority (57%) of the project’s emissions are from combustion in gas turbines, and capture of CO2 from the dilute exhaust is not practical.

Combustion emissions come from burning some of the raw gas arriving at the FPSO, and then more again at the Darwin LNG plant, as fuel to power the purification, liquefaction, product loading and all the other needs of the two sites.

Almost complete removal of CO2 is necessary before gas can be processed to liquefied natural gas (LNG) product.

The first stage of the proposed CO2 removal would occur offshore on the FPSO, reducing the CO2 content from 18 volume percent (v%) to 6v% before the gas is sent by pipeline to Darwin.

The second stage of CO2 separation would take place at the onshore Darwin LNG plant — from 6v% to almost zero.

The CO2 removed (‘captured’ from the methane stream) is simply vented to the atmosphere by design, as in all gas processing and LNG plants, and falsely reported as ‘fugitive’ emissions.

The capture and storage of CO2 from the Barossa project would add substantially to the project’s costs, lengthen its schedule and diminish its viability due to numerous factors.

If the proposal for capture were to go ahead, major changes to the project would need to be undertaken.

The FPSO, currently understood to be in the detailed design phase, would need redesign to include CO2 drying and compression.

The project would need an additional 430km pipeline to carry captured CO2 from Barossa to BayuUndan (and approval sought).

The depleted gas reservoirs at Bayu-Undan must be ‘proven’ good for permanent CO2 storage, to be followed after implementation by regular seismic survey to monitor the spread of CO2 in the reservoir.

The existing compressors on the Bayu-Undan platforms would be unsuitable for CO2 recompression, and different types would be required.

If gas production at Bayu-Undan has completely ceased when the CO2 storage phase begins, the compression gas requirements might have to be supplied from the existing gas export line from Bayu-Undan to Darwin, with backflow occurring from the junction with the new Barossa line.

The reservoir gas component of approximately 0.5 MtCO2/yr captured from the LNG plant feed gas would hardly justify a 500km pipeline to Bayu-Undan for reinjection and storage.

A study just released by IEEFA compares the base case for the Barossa to Darwin LNG development as approved by NOPSEMA with the CCS alternative scenario and a potentially more effective one – electrification.

The table shows the annual quantities of emissions from the four sources in the project (onshore and offshore, combustion and captured and vented) for the three scenarios.

All in all, this makes both the Barossa LNG product and the development project itself in need of being reconsidered or abandoned.

John Robert is a guest contributor with the Institute for Energy Economics and Financial Analysis (IEEFA)

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…