Brigalow, the little solar farm that could, sending power to grid in Queensland

Published by

The 35MW Brigalow Solar Farm in Yarranlea, near Pittsworth, in Queensland has begun sending power to the grid.

The solar farm, which is owned by the solar arm of the Impact Investment Group, has had a rocky road to generation, marked by a legal battle with the Queensland government and a brush with fire in September of last year.

The legal battle came about when the managers of Brigalow – Maryborough Solar – filed a claim in the Queensland Supreme Court arguing that a state-government led rule change affecting solar installations would add around $2.6 million to the cost of the Yarranlea project, which at that time was already under construction.

The rule change, which was for a short period of time brought into effect in the state last year, required licensed electricians to mount and fix solar panels on PV projects of 100kW and larger – a job that had been performed by unskilled labourers and trades assistants.

Industry fought the rule from its inception, arguing that the new safety measure was a “ridiculous” overreach, and that it would cost jobs and blow out the costs and schedules of projects already under development. For projects in the planning stages, it threatened to rule them out completely, they said.

But it was the Brigalow solar farm that won the day. As we reported at the time, the Supreme Court found in Maryrorough Solar’s favour, and declared the government’s rule change “invalid” – a decision that was upheld up in a subsequent appeal – forcing the minister for industrial relations back to the negotiating table.

Welcome to the grid, Brigalow. More power to you! Credit for the chart, as always, goes to Paul McArdle from Global Roam, the providers of our popular NEM-Watch widget.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024