Utilities

Bouldercombe big battery back in action after cause of fire identified

Published by

The Bouldercombe big battery has resumed its commissioning process after releasing a report last week that identified the cause of the fire in September in one of the project’s Tesla Megapack battery modules.

The fire in the 50 MW/100 MWh battery caused a brief but spectacular blaze and brought the commissioning of the project to a halt while the cause was investigated. The fire has been blamed on a fault in the power interface with the grid, and not within the Megapack battery itself.

Testing for the commissioning process has resumed and Genex expects full commissioning to be completed by the middle of the month, although that will initially occur with only 38 of the 40 Megapack modules as Tesla replaces two units affected by the incident. Those replacements will arrive in early December.

“The failure has been isolated to the power electronics interface with the AC bus bar in the individual Megapack unit itself and not the broader installation of Megapack units,” Genex said in a statement last week.

“In order to mitigate against a further event, Tesla will be undertaking replacement of two identified power electronics units and out of caution, physical inspection of the power electronics within the remainder of units at the Project site.

“Genex will also be implementing upgrades to breaker control setting response times to further mitigate against a potential future event.”

The incident was described as a “low intensity fire” that was allowed to burn out with no water required to be used on the fire itself.

The Bouldercombe battery will be the second big battery to be commissioned on the Queensland grid, which remains the most coal dependent in the country, although with plans to reach 85 per cent renewables by 2035.

The first battery was opened at Wandoan South, while the biggest in the state is under construction at Neoen’s Western Downs energy hub, and was recently expanded to a capacity of 270 MW and 540 MWh. That battery will also be using Tesla Megapack technology.

Other big batteries are being planned at or near the state’s main coal generators, including at Kogan Creek (the Chinchilla and Ulinda batteries), at Stanwell, Callide and Tarong.

Genex is also building the first pumped hydro project in Australia in nearly 40 years, the 250 MW, eight hour Kidston project in north Queensland that is located in a former open pit gold mine. Main tunnelling was completed last week.

Genex owns two 50 MW operating solar farms – at Kidston and Jemalong in NSW, and is looking at a 258 MW wind addition to the Kidston hub, as well as what could be a 775 MW solar farm at the Bulli Creek solar and battery hub after landing an off take deal with Andrew Forrest’s green hydrogen project at Gibson Island.

Kidston is also eyeing battery storage as the next stage of the Bulli Creek project, with a potential capacity of 400 MW and at least two hours of storage.

“As coal exits the system we expect further strain on existing plant and the network – further increasing volatility and driving returns for our storage portfolio,” the company said in a presentation to investors last week.

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Contested HumeLink transmission line gets federal green tick to connect Snowy 2.0 to the grid

Transgrid’s massive HumeLink transmission line, considered crucial to unlocking capacity of Snowy Hydro 2.0, has…

19 December 2024

US DoE report busts LNG myth, says fossil gas exports are bad for consumers and the planet

US Department of Energy has eroded the fossil fuel industry's arguements for ramping up fossil…

19 December 2024

“Eye glasses for the grid:” New rules pave way for consumer energy to compete with coal and gas

New rule change is progress for Australian consumers seeking to get the most out of…

19 December 2024

“A weapon for deep sea wind power:” Goldwind rolls out first 22MW offshore turbine

Goldwind says its first 22 ME offshore wind turbine will be a "weapon" on costs,…

18 December 2024

Solar swing state: From nearly too much grid demand to warnings of not enough in less than a day

In less than 24 hours Victoria went from having record demand to warnings of having…

18 December 2024

Zen inks deal with pumped hydro and hydrogen hopeful to help large energy users kick fossil habit

Zen Energy signs memorandum of understanding to develop a smart software based "24/7 Sustainable Energy…

18 December 2024