Bouldercombe battery back on line just 48 hours after fire destroyed Tesla Megapack

Published by

The Bouldercombe big battery near Rockhampton in Queensland has come back on line, just 48 hours after shutting down when a fire erupted in one of its Tesla Megapack battery modules.

The fire on Tuesday night took the battery facility offline after it erupted in the early evening, but the damage was contained to a single module, and the fire is now out, according to project owner Genex Power.

Data from PocketNem shows that the Bouldercombe battery – rated at 50MW and two hours of storage (100MWh) operated at low levels on Thursday evening, charging at rates of just over 5MW in the early evening, and discharging smaller amounts back into the grid.

The battery had been operating at or near full capacity in the days leading up to the fire as it worked through the final phases of its commissioning process, which owner Genex Power had expected to complete by late October.

CEO Craig Francis told RenewEconomy on Friday that auxiliary power had returned to the site, and a controlled charge was performed on Thursday night into the Tesla Megapack modules. There are, or were, a total of 40 Megapack modules on site before the fire.

Francis said the re-energisation showed that the facility had the confidence of the Australian Energy Market Operator, and the transmission company Powerlink, although full operations will not resume until a root cause analysis is complete.

A fire in a Tesla Megapack during the commissioning process of the Victoria Big Battery near Geelong in 2021 was ultimately blamed on a liquid coolant leak. In that incident, two Megapack modules were destroyed, but it did not significantly delay the project commissioning.

The cause of the Bouldercombe battery fire is not yet known, including whether a fault occurred within the battery module or on the other side of the inverter.

The quick return to service at both the Bouldercombe and the Victoria Big Battery projects contrasts with the catastrophic nature of events such as the explosion at the Callide coal plant two years ago. That facility remains off-line, and with a growing repair cost in the hundred of millions of dollar.

See also: Two new big batteries in South Australia sign connection deals, including first for Zen Energy

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Solar and wind deliver November generation high, closing out a record spring

New monthly data from Rystad Energy shows utility wind and solar generation exceeded 4 terwatt-hours…

3 December 2024

Big battery summer: AEMO says new storage capacity to play key role in keeping lights on

AEMO says its ability to deal with summer heat and floods have been boosted by…

3 December 2024

Construction complete at Victoria’s second-biggest battery, contracted to Big Oil company

Construction has been completed on the second biggest battery in Victoria, which will be the…

3 December 2024

Expensive failure: Flagship Gorgon CCS collects less CO2 in worst year

Chevron's Gorgon CCS project - the flagship for the technology in Australia - has had…

3 December 2024

“No-cost” home solar and battery start-up raises funds to target 2,000 homes a month

Sydney-based pioneer of no-cost solar and battery service closes $4.28 million funding round towards plans…

3 December 2024

How to make the rooftop solar emergency backstop work for consumers

Rather than relying on a big solar button, rapid rule changes could help AEMO manage…

3 December 2024