Press Releases

Blades now turning at Acciona’s Mt Gellibrand wind farm

Published by

PRESS RELEASE

.         Commissioning process under way
·         Full production scheduled for August

The first turbine has now been switched on and the blades have started turning, generating the first megawatts of renewable energy at ACCIONA’s Mt Gellibrand wind farm in Victoria.
A commissioning process designed to test the turbines and their electrical connections is now under way. As the 44 turbines come online, energy production will ramp up to around 66MW in July, and the full 132MW capacity in August. Total output will power approximately 60,000 homes.
Construction work began in April 2017 and is now largely complete, with most turbines finished and just a few remaining blades to be installed over the coming days. Civil, substation and electrical works are now complete, laying the groundwork for commissioning. 
“It’s a great moment for the team, the local community and Victoria,” said Brett Wickham, ACCIONA Energy Australia’s Managing Director.
“This project represents a $258 million investment in the state and in the Australian renewables sector.  We are immensely proud to see energy production starting. We are also grateful to the local community for their support over the past year, and to all the employees and local contractors for their hard work and dedication in reaching this milestone.”
The construction of the project followed a public tender process, in which the Victorian Government committed to purchasing the renewable energy certificates generated from 66MW of Mt Gellibrand. These certificates will contribute to the state’s renewable energy generation targets of 25 per cent by 2020 and 40 per cent by 2025.
Mt Gellibrand will be ACCIONA Energy’s fourth wind farm in Australia, after Cathedral Rocks (64 MW in South Australia), Waubra (192 MW in Victoria) and Gunning (46.5 MW in New South Wales). Australia, where ACCIONA has 302.5 MW, ranks fourth in the company’s portfolio of wind assets after Spain, the USA and Mexico.
In addition to developing company-owned facilities, ACCIONA previously built and commissioned a photovoltaic plant near Canberra for a third party, with a rated capacity of 20 MW.
Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024