Bigger than Godzilla: Fortescue receives second shipment of turbine parts to top “self-lifting” towers

Published by

A second shipment of some of the biggest wind turbine parts yet seen in Australia, including the longest blades, has arrived in Port Hedland in Western Australia’s far north, en route to their Fortescue’s first wind farm in the Pilbara.

Fortescue has posted an update on the progress at its 133 megawatt (MW) Nullagine wind project, where the iron ore giant is testing a unique “self lifting” wind tower technology developed by Spain’s Nabrawind, now owned by Fortescue.

Topping the towers will be Envision’s technology, including 89 metre long blades, twice as long as a Boeing 737, according to Fortescue.

“With the second vessel now in port carrying the next set of parts, the operation is gathering pace,” Fortescue said in a post on LinkedIn on the weekend.

“We’re transporting these beasts 300 kilometres from Port Hedland to Nullagine, where we’re building a 133 MW wind farm to help power our operations with renewable energy.”

As Renew Economy has reported, Envision are also supplying the same 7.8 megawatt turbines – the most powerful to be deployed in Australia – to the Narrogin wind farm south of Perth, which began construction in July after project owner Neoen struck a long term offtake agreement with Synergy.

For Fortescue, the Nullagine wind project will be followed by a bigger wind project at the neighbouring Bonney Downs facility, along with 1.4 GW of solar that is currently being delivered elsewhere in the Pilbara.

The self lifting turbine tower technology allows for simpler and quicker erections, less concrete, and elevates the blades themselves to where there is generally more wind.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by
Tags: Fortescue

Recent Posts

Changing tack on Victoria’s energy transition will throw electricity savings into reverse, experts warn

One Nation and Coalition plans to review or roll back Victoria's energy policies would likely…

31 August 2026

“Smart switch:” Retailer tests time-of-use plans in bid to slash bills of hardship customers

State-owned retailer will pilot time-of-use electricity plans across 5,000 select households, to see how much…

31 August 2026

From solar cells to solar farms: Quest for ultra-low cost PV gets $100 million federal boost

Australian Renewable Energy Agency will invest more than $100 million across 20 research and development…

31 August 2026

SwitchedOn podcast: How three hours of free solar power can cost you more

Solar Sharer exposes a fundamental problem with our energy system - protecting retailer revenues can…

31 August 2026

Rooftop solar record tumbles as battery rebate drives 1 GW of new installs over just three months

April to June quarter delivers new records for home batteries and large-scale solar investment, but…

31 August 2026

Why we need regional leaders for renewable transition | Energy Insiders

Sabiene Heindl from The Energy Charter on the need for strong regional leaders for transition…

31 August 2026