Policy & Planning

Big battery in middle of Sydney forced to planning review by residents of tiny towns 800 km away

Published by

A major battery storage project located in the centre of Sydney has been forced to review by an independent panel after a volley of protests by residents of two tiny towns located around 800 kilometres away.

Ausgrid, which operates the local electricity network in much of Sydney and to the north of the state capital, wants to build a 200 megawatt (MW), 431 MWh battery in Homebush, next to an existing sub-station and right next to the M4 Western Freeway.

The $215million battery will be located 13 kms from the Sydney CBD and not far from the geographical centre of the Sydney metropolitan area.

It is one of at least 7 new big battery projects proposed for the greater metropolitan area in Sydney and Ausgrid argues that the Homebush battery is needed to boost grid reliability and security, and reduce the need for new transmission lines.

The Homebush battery proposal received 63 submissions, including 59 objections. A project must be referred to the Independent Planning Commission if 50 or more people object.

But the NSW Planning website reveals that 19 of the submissions opposing the project came from interstate – with just one opponent living within 5 kms of the project site.

Intriguingly, 12 of the submissions opposing the project came from Moulamein, a tiny town with a population of less than 500 that is located 806 kms from Sydney in the south-west of the state. Six came from the nearby small town of Barham, located 823 kms from Sydney.

There were a number of other submissions opposing the project from nearby towns such as Swan Hill (7) and Gannawarra, and from various “Save our Surroundings” organisations scattered across the same area.

Almost all were anonymous – apart from the serial objector Ian McDonald (from Walcha in New England), who said governments are putting renewable targets ahead of the nation’s public health and food security.

Other concerns that were cited by objectors included the usual fears about fire safety, pollution, waste, traffic (it is right next to a major freeway) and – less plausibly in this instance – concerns about the impact on agricultural land.

It is one of the most striking examples of the ability of special interest groups to hijack the planning process in the state of NSW, affecting wind, solar and battery projects and transmission lines.

Most objectors made clear they simply don’t like the idea of renewables and think that climate sciences is a “con”.

One submission said the battery would ensure “cyber warfare” in the heart of Sydney, alleging that the battery could be forced by foreign entities – through remote controls – to shut down, overheat or extract data from the local area.

The 12 submissions from Moulamein and surrounding areas were strikingly similar, usually a one or two sentence question, and often with poor spelling.

“Does this BESS project align with Sydney’s long-term renewable energy goals, or is it just a stopgap?” wrote one. “What plans have been put in place for server (sic) weather events.”

Another from Moulamein expressed concern about “noise and light” from the battery, which is located at the junction of two major freeways. “What mitigation plans have been considered? were local resedender (sic) involved in the process?”

Another from nearby Swan Hill asked: “How will this installation affect property values for those living within a kilometre of the site? Have residents in the surrounding suburbs been mad (sic) aware?”

There were also a handful of submissions from local residents, and from the local Discount Shopping outlet operator, Vicinity Centres, which did not object but was concerned about the view from its car parks and suggested the use of colour bond fences as mitigation.

The NSW Planning department says the project “would not result in significant impacts on the local community or the environment, and any residual impacts can be managed through conditions.”

Submissions to the IPC are open until July 17. There is no plan for a public meeting. The IPC recently had to cancel a proposed meeting for a contested solar and battery project, because none of the mostly long distance objectors to the project that forced it to the review panel bothered to turn up.

Ausgrid hopes to begin construction of the battery this year.

If you would like to join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, you can click here to subscribe to our free daily newsletter.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Please click here. Your support is invaluable.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

State’s stand-alone solar fail: The energy transition should deliver more than a new landlord

Western Power's stand-alone power system program is not an energy transition solution. It is a…

10 July 2026

Energy Insiders Podcast: Electric truck network starts to take shape

Electric trucks are suddenly big news in Australia. We catch up with NewVolt's Anthony Headlam…

10 July 2026

Watchdog warns spike in home battery complaints could damage consumer trust

Home batteries are flying off shelves and the consumer watchdog wants stronger protection to maintain…

10 July 2026

Offshore wind developers pray for bipartisan support ahead of key state election

Victoria's offshore wind developers are much more optimistic than they were a year ago, but…

10 July 2026

State utility bets on Australian-first compressed CO2 “energy dome,” with up to 12 hours of storage

Victoria's Latrobe Valley will soon host a ground-breaking long-duration energy storage facility capable of continuously…

10 July 2026

“It’s nuts:” Wind developer forced to truck giant transformer thousands of kilometres after port refusal

Renewable developer says the refusal of its closest port to handle a giant transformer has…

10 July 2026