Bidders in Germany’s largest ever offshore wind auction forgo subsidies

Published by

Investors are willing to build offshore wind farms in German waters in the Baltic and North Sea without state support, and will now even have to pay to be awarded a contract.

In the country’s largest offshore auction to date, which totals 7 gigawatts (GW), several participants submitted “zero cent” bids for all four sites on offer, meaning they don’t require subsidies, the country’s grid agency BNetzA has said.

As a consequence, the agency will now start a “dynamic bidding” process, where investors will have to specify how much they are prepared to pay, and the highest bidder will be awarded the contract.

BNetzA head Klaus Müller called the tender results “good news for Germany’s energy transition,” given that the lion’s share (90%) of the proceeds from the auction will be used to lower electricity costs, with the remainder to be spent on marine environment protection and sustainable fishing.

Germany aims to increase its offshore capacity to 30 GW by 2030, and the current auction is the country’s largest ever by far. The capacity on offer almost matches the country’s entire existing offshore wind capacity of around 8 GW.

Some of the auctioned areas still require environmental assessments, which will need to be conducted by the bidders.

The cost of constructing new offshore wind farms has fallen markedly in recent years, making it one of the most reliable and profitable renewable power sources on the market.

Germany plans to greatly increase its offshore capacity in a bid to reach its ambitious renewable power share target of 80 percent by the end of the decade.

This article was originally published by Clean Energy Wire. Republished here with permission. To read the original version of the story, click here.

Share
Published by

Recent Posts

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024

Solar Insiders Podcast: A roller coaster year in review – and the keys to a smoother 2025

In our final episode for the year, SunWiz's Warwick Johnston on the highs and the…

20 December 2024

CEFC creates buzz with record investment in poles and wires, as Marinus bill blows out again

CEFC winds up 2024 with record investment in two huge transmission projects, as Marinus reveals…

20 December 2024

How big utilities manipulate the energy market, even with a high share of wind and solar

Regulator says big energy players are manipulating prices to their benefit. It's not illegal, but…

20 December 2024