Beryl solar farm reaches full output after single month of commissioning

Published by

It’s not all doom and gloom out there in the world of renewable energy project development and the trials and tribulations of commissioning on Australia’s main grid.

The Beryl solar farm, has reached full and unrestrained output after barely a month working through the commissioning phases after energisation of the plant was first achieved.

It’s unclear if that is a record, but it must be close, particularly given the recent delays which have hamstrung projects such as Adani’s Rugby Run solar farm in Queensland, and Windlab’s solar, wind and battery hub at the Kennedy energy hub.

And, of course, connection delays have been one of the main problems affecting EPC contractors RCR Tomlinson, which went bust, and others who have had to take a big hit on project costs or be pinged for damages because of the delays.

The Beryl solar farm, built by Downer Group on behalf of First Solar, and now owned by the listed company New Energy Solar, is an 87MW project located north of Mudgee, whose output is contracted to the NSW state government, specifically for its NW Metro project.

It began production in late April, and reached full output in less than one month, and 33 days from first energisation.

‘When good site selection, capability, planning, experience and cooperation of all stakeholders come together, connection to the grid can be readily and timely achieved, as has been the situation with this project,” said Steve Jackson, First Solar’s Asia Pacific regional manager.

“Development and delivery of the Beryl project has been a great team effort and I’m really proud of the work of all involved.”

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

If Australia is serious about 1.5°C, it needs to shut down coal by 2034 and install a lot more solar and batteries

If Australia got serious about climate and 1.5°C, what would it need to do on…

29 June 2026

Australian researchers test new tech to help smash the solar ceiling, bring PV to apartments

A UNSW pilot will test the ability of an artificial intelligence-powered energy system to help…

29 June 2026

Households are about to be offered 3 hours of free power. Who should sign up, and who should think twice?

This week marks the launch of federal Labor's Solar Sharer Offer. Here's how it will…

29 June 2026

Slimmed-down wind and battery project receives state planning approval, solar component dropped

World's biggest independent renewable developer gets state planning approval for a slimmed down wind and…

29 June 2026

Game changer for EVs? Australian battery pioneer lands $45m grant for silicon anode that boosts energy density

An Australian battery technology pioneer has landed a major government grant to start commercial production…

28 June 2026

“I didn’t notice:” Homeowners using solar, batteries and V2G to stay connected in blackouts

Could your electric car do more than just keep the lights on in an emergency?…

28 June 2026