Beryl solar farm reaches full output after single month of commissioning

Published by

It’s not all doom and gloom out there in the world of renewable energy project development and the trials and tribulations of commissioning on Australia’s main grid.

The Beryl solar farm, has reached full and unrestrained output after barely a month working through the commissioning phases after energisation of the plant was first achieved.

It’s unclear if that is a record, but it must be close, particularly given the recent delays which have hamstrung projects such as Adani’s Rugby Run solar farm in Queensland, and Windlab’s solar, wind and battery hub at the Kennedy energy hub.

And, of course, connection delays have been one of the main problems affecting EPC contractors RCR Tomlinson, which went bust, and others who have had to take a big hit on project costs or be pinged for damages because of the delays.

The Beryl solar farm, built by Downer Group on behalf of First Solar, and now owned by the listed company New Energy Solar, is an 87MW project located north of Mudgee, whose output is contracted to the NSW state government, specifically for its NW Metro project.

It began production in late April, and reached full output in less than one month, and 33 days from first energisation.

‘When good site selection, capability, planning, experience and cooperation of all stakeholders come together, connection to the grid can be readily and timely achieved, as has been the situation with this project,” said Steve Jackson, First Solar’s Asia Pacific regional manager.

“Development and delivery of the Beryl project has been a great team effort and I’m really proud of the work of all involved.”

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Re-linking the NEM: could fungible ESEM ‘bulk energy’ contracts be bankable?

Almost three decades after its inception, the NEM has a rare chance to re-link the…

30 October 2026

Crossing 1.5°C is a call to urgent action

Every fraction of a degree matters and increases risks to people, communities and ecosystems.

30 October 2026

“Tipping point”: Australia’s appeal to global offshore wind farm investors hangs in the balance, conference hears

Australia's appeal to potenntial international offshore wind farm investors won't last forever, All Energy conference…

30 October 2026

Australia’s most successful renewables and storage developer seals huge debt deal to pay way for next round of projects

Australia's most successful renewable and storage developer raises $A1.8 billion in new debt to refinance…

30 October 2026

Big savings, big barriers – getting Australian business off gas | SwitchedOn Australia

From swimming pools to factories, heat pumps are proving their worth, but getting off gas…

30 October 2026

A scan of the Anthropic IPO: How to price the AI worry and the dream

Anthropic's IPO is really a bet on how much better AI will get. But to…

30 October 2026