It’s not all doom and gloom out there in the world of renewable energy project development and the trials and tribulations of commissioning on Australia’s main grid.

The Beryl solar farm, has reached full and unrestrained output after barely a month working through the commissioning phases after energisation of the plant was first achieved.

It’s unclear if that is a record, but it must be close, particularly given the recent delays which have hamstrung projects such as Adani’s Rugby Run solar farm in Queensland, and Windlab’s solar, wind and battery hub at the Kennedy energy hub.

And, of course, connection delays have been one of the main problems affecting EPC contractors RCR Tomlinson, which went bust, and others who have had to take a big hit on project costs or be pinged for damages because of the delays.

The Beryl solar farm, built by Downer Group on behalf of First Solar, and now owned by the listed company New Energy Solar, is an 87MW project located north of Mudgee, whose output is contracted to the NSW state government, specifically for its NW Metro project.

It began production in late April, and reached full output in less than one month, and 33 days from first energisation.

‘When good site selection, capability, planning, experience and cooperation of all stakeholders come together, connection to the grid can be readily and timely achieved, as has been the situation with this project,” said Steve Jackson, First Solar’s Asia Pacific regional manager.

“Development and delivery of the Beryl project has been a great team effort and I’m really proud of the work of all involved.”

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Energy Insiders Podcast: Dutton’s high stakes, low sense nuclear plan

In this episode we take a quick look at the Coalition’s nuclear plan and its…

13 December 2024

Is big tech going all in on nuclear? Google and Microsoft have just pledged $45 billion on renewables

In just the last week Microsoft and Google have pledged $50 billion in spending on…

13 December 2024

The Coalition’s master plan: Bring large scale wind, solar and battery storage installations to a halt

The Coalition nuclear plan would largely bring investment in large scale renewables and storage to…

13 December 2024

Victoria forges ahead on electrification, with proposal to kick gas out of existing homes

Victoria launches consultation on the next step its Gas Substitution Roadmap, including options to extend…

13 December 2024

Peter Dutton’s nuclear plan: Mad, bad, and extremely dangerous

It might seem weirdly appropriate that Peter Dutton should release his nuclear power policy costings…

13 December 2024

Frontier Economics and its “house of cards” case for nuclear

Frontier’s arguments hold no more water than any other nuclear advocate, and their assumptions are…

13 December 2024