It has been revealed that output from the newly-sold Beryl solar project west of Gulgong  will be used to power the NSW government’s new north-west rail line in Sydney, and may add battery storage as an extra revenue source.

Beryl reached financial close in May, as we reported at the time, but while the financing was built around a 15-year power purchase agreement with the NSW government to offset the entire operational electricity of the new Sydney Metro Northwest railway, that detail was not released at the time.

RenewEconomy only received official confirmation when New Energy Solar announced on Monday it would buy the 87MW solar farm, although it appears the NSW quietly released details two weeks ago, with no media publicity.

Just why the NSW government should be so bashful about the project is not clear, although one could speculate it has something to do with the internal dynamics of the state conservative government and their federal counterparts – none of whom have ever been seen at the opening of a wind or solar farm.

The New Energy Solar documents provide some interesting insight into the solar farm (see details above), and says it will have a yield of 8.2 per cent – much higher than its 6.8 per cent average from its mostly US-based portfolio, and also the recently purchased Manildra solar farm – also bought from First Solar.

The $187 million solar farm – that’s the cost of construction, not the sale price, which is not disclosed – is underpinned by the 15-year contract with the NSW train project, which will account for 134,000MWh, or 69 per cent of the output.

Without a confirmed sale price, it is difficult to analyse exactly what sort of price that equates to. Morgan Stanley analysts suggest a PPA price of $78/MWh, including the LGCs (large scale certificates), and an overall return of around $90/MWh.

That premium will be delivered either through the merchant market – where wholesale electricity prices remain high, and the LGC spot market could stay high for another two years before contracting sharply – or other PPA contracts.

New Energy’s head of investment Liam Thomas says battery storage also remains an option – presumably to time shift the output of the solar farm, and sell in evening peaks rather than the anticipated price troughs in the middle of the day, and/or to provide market services.

“The project provides stable $A cashflow under the long-term PPA with TfNSW (Transport NSW),” he said in a statement. “The PPA structure, under which the majority of the off take is contracted, is consistent with our strategy to secure predictable, low-risk returns for investors.”

New Energy Solar will buy 49 per cent of the Beryl project from First Solar now, and the rest on completion of the project, expected in mid 2019. The project is being built by Downer Group.

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024