Battery hopeful licks its wounds after missing out on capacity credits as grid shortfall erased

Published by

Frontier Energy, an ambitious renewable and energy storage developer with former W.A. premier Mark McGowan soon to take its helm, has been forced to reassess plans for its first major solar and battery storage project after missing out on a key and lucrative tender.

The Perth-based company has been working on the  80 MW/360 MWh Waroona battery project near Wagerup that was to be paired with a solar farm.

It had been one of a half a dozen battery projects that had passed initial assessments and were lining up for the annual allocation of capacity credits in the state for 2026/27 – the most ever and a significant reshaping of the state’s grid as it accelerates its transition away from coal.

But Frontier missed out. A batch of new and existing battery projects – including the two stages of the Kwinana battery, the two giant Collie batteries being built by Neoen and Synergy, Alinta’s Wagerup battery, Naturgy’s Cunderdin solar battery and Atmos Renewables’ Merredin battery – landed the lucrative contracts, worth $230,000 a megawatt a year.

Frontier – which has been remarkably candid about its battery project economics and its prospects, partly because it is a listed company and also because it also seems to like talking about it – says it drew the short straw.

It had wanted to land a five year fixed contract under the terms of its proposed $215 million financing arrangement with Infradebt, but this was not possible because the sizeable supply shortfall for 2026/27 forecast by the market operator no longer existed – thanks to the success of another scheme designed the W.A. grid’s problematic solar duck.

Those contracts, known as NCESS, have underwritten both the Neoen Collie battery, which will be the biggest in Australia when complete at 560 MW and 2,240 MWh, and the Synergy Collie battery, also sizeable at 2,000 MW. It has also helped the Alinta battery (100M, 200 MWh), and the second state of the Kwinana battery (200 MW, 400 MWh).

It meant that the forecast 1,00 MW deficit was eliminated and the market operator found itself with surplus reserve capacity, so much so that it now assumes that one of the ageing coal generators at Muja will be closed that year.

The market responded savagely to the news, marking down the company’s share price by nearly half, leaving it at just one quarter of its value from August.

Frontier says it is now regrouping and looking at other finance options to progress the Waroona project, although it conceded it will be delayed.

It has, for instance, thrown its cap into the ring for yet another program, the federal government sponsored Capacity Investment Scheme, which is seeking 500 MW and 2,000 MWh of battery capacity.

“Whilst the outcome of AEMO’s allocations is not ideal, energy prices remain at record highs, and are forecast to continue into the future, the underlying fundamentals for our Waroona Renewable Energy Project remain excellent,” CEO Adam Kiley said in a statement, citing anticipated higher wholesale electricity prices.

In a conference call with investors on Wednesday, Kiley defended the decision to punt on a five-year financing strategy, saying that if it sought just a one year contract it would have likely landed it – but the $19 million it would have received would have required a completely different funding strategy.

He says, however, that it will not seek a five year contract in the next round.

The company is hopeful that its chances in the CIS remain good, given its focus on hybrid facilities and standalone batteries, the lack of available new renewable projects in the state, and that the fact that projects which have already received contracts through the NCESS are excluded.

“The Company will now pursue multiple funding solutions that were not previously fully examined due to our RCC expectations. These include project bonds, equipment financing, and equipment supplier equity opportunities for fixed equipment,” the company said in a statement.

Asked if McGowan still intended to join the board and take the role as chair in october, Riley said: “Obviously he’s quite surprised and a bit shocked as the rest of management, as well as the board, regarding the outcome regarding reserve capacity,, but when I was speaking to him (yesterday) that was still the intention.”

See also: Renew Economy’s Big Battery Storage Map of Australia.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Renewables sector learning from messy failures after oil company collapses with $200m clean up bill

Another oil and gas company collapse raises new concerns about who picks up massive clean…

15 July 2026

Data centres will have “legal obligation” to BYO renewables, says PM, but LNP looms as spoiler

PM says data centres will have a "legal obligation" to meet their own energy needs…

15 July 2026

SwitchedOn podcast: Why the booming home battery market is staying clear of virtual power plants

Despite the potential for lower bills, and a stronger grid, most battery owners still aren't…

15 July 2026

Flood-prone rugby fields, gaps in regional health: First round of REZ grants back 46 community projects

New drainage systems for flood-prone sports ground and a new community health hub are among…

15 July 2026

Coal closure plan urgently needed as unreliable clunkers push power prices through roof

The growing unreliability of end of life coal fired power plants is costing Australians and…

15 July 2026

Rinehart-backed miner signs deal to make magnets for wind turbines and EVs

A Rinehart-backed miner has signed a deal to partly fund and supply rare earths for…

15 July 2026