AVL finishes electrolyte factory, no word on when first vanadium flow batteries will be made

Published by

Australia Vanadium (AVL) says has finished building its Western Australia vanadium electrolyte manufacturing facility, although commissioning has slipped into 2024.

The electrolyte will initially be sold only to the company’s battery subsidiary VSUN Energy, and be made in batches to order.

An AVL spokesperson says the company is currently building the prototype of its first residential vanadium redox flow battery (VFRB). For other VSUN Energy projects in future the company will buy the battery ready made but use its in-house vanadium electrolyte.

The factory, in the Perth suburb of Wangara, has a maximum production capacity of up to 33 megawatt hours (MWh) of electrolyte a year, a volume it will be capable of producing as soon as it is commissioned in the first quarter next year.

In March, when the company was still expecting commissioning to happen in September this year, CEO Graham Arvidson told RenewEconomy that around 70 litres of electrolyte is needed to generate a kilowatt hour (kWh) of energy, suggesting the plant will be able to produce up to 2.31 million litres of electrolyte a year. 

About 6600 pounds of vanadium pentoxide-equivalent feedstock is required to make a 300 kWh battery.

Although the biggest individual lithium-ion batteries are being measured in the hundreds of megawatt hours and sometimes gigawatt-hours, VSUN Energy’s batteries are a touch smaller, meaning the new factory should be able to produced enough electrolyte for multiple batteries a year.

To date VSUN has been contracted for a 78kW/220kWh battery for Western Australian power company Horizon Power to test at Kununurra; a 5kW/30kWh battery to power a water purification chlorinator for Water Corporation WA; a 300 kWh version for battery metals miner IGO; and a 20kW/80kWh battery for an apple grower in Victoria.

The company has been working at commercialising its batteries for several years.

Last year it signed a deal with Sydney-based newcomer North Harbour Clean Energy to find and develop grid-scale opportunities for “Australian invented” long-duration battery storage technology.

Mine-to-battery goal

AVL’s factory was estimated in 2021 to cost $7.4 million and despite construction costs skyrocketing, Arvidson said earlier this year the project was on budget.

If this first factory works as intended, the company plans to build other versions around Australia.

The factory uses technology licensed from US Vanadium to make the electrolyte, for which AVL holds the local licence to use, which is supplying the vanadium pentoxide feedstock needed to make the electrolyte while the mine is still being developed.

Eventually, AVL plans to source its own feedstock from its eponymous yet-to-be-commissioned project at Garabintha, near Meekatharra in Western Australia.

Most of a federal grant of $3.69 to support modern manufacturing went towards building the factory, AVL says.

Vanadium batteries are attractive as a long-duration energy storage option because of their ability to store large amounts of energy, their 20 year lifespan, a very high cycle performance, minimal degradation, and for being safe and non-flammable.

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Rachel Williamson

Rachel Williamson is a science and business journalist, who focuses on climate change-related health and environmental issues.

Share
Published by
Tags: flow battery

Recent Posts

Australia’s biggest coal state breaks new ground in wind and solar output

New South Wales has reached two remarkable renewable energy milestones that signal the growing contribution…

6 January 2025

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024