Australia’s largest solar PV plant to begin feeding grid in next week

Published by

PV Magazine

The Nyngan project will bring 102 MW of large-scale solar to the Australian grid, with 53 MW to follow at Broken Hill. wikimedia commons 

First Solar’s Nyngan solar plant, which will be 102 MW once completed in July, has connected to the grid at 25MW. The plant will be Southern Hemisphere’s largest for a short while.

Australia’s Nyngan solar plant – a 102 MWPV project set in western New South Wales – will begin feeding the grid this week as the first portion of the plant comes online.

Beginning at 25 MW, the First Solar-developed operation will be fully connected at 102MW by July, making it the largest single PV installation in the Southern Hemisphere, at least until a 141 MW solar plant in Chile – also being developed by First Solar – is connected later this year.

First Solar has partnered on the Nyngan project with local renewable energy developer AGL Energy Ltd. Construction of the US$220 million project began last January, and the millionth solar panel was installed just last week – on budget and on schedule.

“What was really constraining the large-scale solar market was the fact that it just hadn’t been done before, so there was a lot of misconception around the execution and cost challenges,” said First Solar’s Asia-Pacific manager Jack Curtis. “It can only get more efficient.”

First Solar and AGL are also collaborating on another large-scale PV project in New South Wales – a 53 MW solar plant in Broken Hill, a little to the west of the Nyngan project. Combined, these two solar plants are expected to cost AUD$440 million ($337 million), of which around 50% funding is coming from the Australian and state government.

Once finalized, both projects will generate enough clean solar energy to power 50,000 New South Wales households, and will add to the projected 4.1 GW of large-scale solar PV capacity forecast for installation in Australia between now and 2021.

Source: PV Magazine. Reproduced with permission.

Share
Published by

Recent Posts

Rio Tinto says wind and solar make economic sense, but LNP stands in way of its plans to save smelters

Rio Tinto boss says renewables are essential for the future of its assets. But the…

29 January 2025

Renewable records surge across the grid in midst of latest heatwave

Wind and solar set new output records in NSW and across the main grid amid…

29 January 2025

Global battery project developer mourns “sudden passing” of Australian head

Italian-based battery storage and EV charging company announces sudden passing of its Australian boss.

29 January 2025

Contractors named for new 12GWh pumped hydro storage project

Contractors named for early works on potential 12 GWh pumped hydro project - assuming the…

28 January 2025

Amazon taps into new Victoria wind farm even as its boss courts favour with Trump

New 97 MW wind farm in Victoria to help power Amazon's computing and data centre…

28 January 2025

“We’re going to miss the bus” if we wait for nuclear, says new chief scientist

New chief scientist endorses CSIRO GenCoset report and says Australia will "miss the bus" if…

28 January 2025