Australia’s celebrated first shipment of “clean” hydrogen in January this year has become the subject of an investigation by the Australian Transport Safety Bureau, after a flame was seen coming from the gas combustion unit’s exhaust on deck.

In a notice on its website last updated on Tuesday, more than two months after the incident, the ATSB said it was investigating a gas pressure control equipment malfunction on board the Suiso Frontier after the ship had loaded liquefied hydrogen at Western Port, Hastings.

The Suiso Frontier is a Japan-built dedicated liquid hydrogen transport ship that sailed into the history books in January this year for receiving Australia’s first shipment of liquid “blue” hydrogen – produced through a coal gasification process – for delivery to customers back in Japan.

As RenewEconomy reported at the time, this occasion was widely heralded as a major milestone for the Hydrogen Energy Supply Chain (HESC) project and Australia’s emerging status as a hydrogen exporter – even if it was, in this instance the, wrong colour.

It has now emerged that the historical event was not entirely seemless, but marred by what the ATSB has categorised as a “serious incident,” worthy of investigation – even if it did not make the news at the time.

“At 2147 AEST on 25 January 2022, a flame was seen coming from the gas combustion unit’s exhaust on deck. The unit was immediately shutdown and isolated before the crew implemented the fire prevention response plan,” the notice says.

“No further abnormalities were reported and there were no injuries, damage or pollution. As part of the investigation, the ATSB will interview relevant persons and obtain other evidence, including recorded data.”

According to the ATSB notice here, the investigation is currently in the evidence collection phase, with the completion of a report on the incident expected to be completed sometime in the third quarter of 2022.

A statement from an ATSB spokesperson on Friday confirmed with RenewEconomy that the investigation into the incident has been on the public record since it was first published on the Bureau’s website on 31 January.

At that time it was also reported in trade publication Daily Cargo News, although that report is behind a paywall.

A statement from ATSB chief commissioner Angus Mitchell noted at the time that “a team of transport safety investigators from ATSB’s Canberra, Melbourne, and Sydney offices with expertise in marine operations and data recorders were deployed to the site shortly after the ATSB was notified of the incident.”

The Kawasaki-made and HySTRA operated Suiso Frontier has a hydrogen capacity of 1,250 cubic metres, which translates to around 88 tonnes of liquid hydrogen, and is expected to make numerous shipments of hydrogen between Australia and Japan.

At the time of the January shipment, a spokesperson for the HESC project confirmed to RenewEconomy that it involved the transport of just 2.6 tonnes of hydrogen, the majority which was produced using unabated fossil fuels with just one tonne of the hydrogen produced by the HESC project.

That one tonne of hydrogen was produced using brown coal as its primary feedstock – one of the dirtiest forms of fossil fuel – with the hydrogen being made “clean” through the purchase of carbon offsets.

The remaining 1.6 tonnes of hydrogen shipped were confirmed to have been supplied by project partner Coregas.

Representatives of the HESC project told RenewEconomy that this additional hydrogen – which makes up more than 60 per cent of the pilot hydrogen shipment – was produced from fossil gas.

Ultimately, the Suiso Frontier did successfully deliver the world-first Australian shipment of liquefied hydrogen to Japan, arriving in the the port at Kobe on February 25.

Sophie Vorrath

Sophie is editor of One Step Off The Grid and deputy editor of its sister site, Renew Economy. She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

New Year begins with more solar records, as PV takes bigger bite out of coal’s holiday lunch

As 2025 begins, Victoria is already making its mark on the energy landscape with a…

3 January 2025

What comes after microgrids? Energy parks based around wind, solar and storage

Co-locating renewable generation, load and storage offers substantial benefits, particularly for manufacturing facilities and data…

31 December 2024

This talk of nuclear is a waste of time: Wind, solar and firming can clearly do the job

Australia’s economic future would be at risk if we stop wind and solar to build…

30 December 2024

Build it and they will come: Transmission is key, but LNP make it harder and costlier

Transmission remains the fundamental building block to decarbonising the grid. But the LNP is making…

23 December 2024

Snowy Hunter gas project hit by more delays and blowouts, with total cost now more than $2 billion

Snowy blames bad weather for yet more delays to controversial Hunter gas project, now expected…

23 December 2024

Happy holidays: We will be back soon

In 2024, Renew Economy's traffic jumped 50 per cent to more than 24 million page…

20 December 2024