Australia’s biggest wind farm at Coopers Gap to undergo major repairs

Published by

The 458MW Coopers Gap wind farm in south west Queensland, the newest and biggest wind project built to date in Australia – is to undergo major repairs after faults were found in its commissioning process.

AGL, which operates the $850 million project and is a joint owner through the Powering Australia Renewables Fund, said in a statement that the blades of one of the 123 turbines will have to be replaced entirely, while GE Catcon is also going to replace  “generators” – referring to the equipment in the nacelle at the top of the wind tower – in a further 50 turbines.

“During the commissioning process, rigorous tests were carried out to ensure the long-term operational capability and reliability of each component,” AGL said in a statement.

“However, recent testing by GE has identified that one of their wind turbines will need to be replaced. An exclusion zone has been erected around the turbine to ensure safety. GE will also replace a number of generators to ensure long term, reliable operations.”

It is believed that only the blades, and not the tower will need to be replaced, as a result of a fault that has not been revealed. Still, with the blades of the GE measuring 60 metres long, and weighing 22 tonnes, and fixed more than 100 metres in the air, it will be a complex process.

There are 91 GE 3.63MW turbines (137m rotor diameter) installed at the site, and 32 GE 3.83MW (130m rotor diameter) turbines.

In its own statement, GE said: “During GE’s routine inspection and testing, it was identified that one of the turbines will need to be replaced.  This turbine has been taken out of service while the Coopers Gap project continues to remain operational.

“GE takes reliability of our equipment seriously and is taking a proactive approach to change out generators, a component inside the nacelle, in 50 of the turbines. We have already commenced planning for a repair program conducted in phases to minimise disruption.”

GE said the repairs would be conducted one turbine at a time. It did not give an indication of the cost or timetable of the project.

The issues at Coopers Gap – located 260kms north west of Brisbane between Dalby and Kingaroy – add to a terrible run of issues for some of Australia’s largest wind farms, including the delays to commissioning of the 336MW Dundonnell wind farm – and the fall of a blade from one of its turbines that stopped all production for several days.

Other major wind farms are also taking much longer to be completed than originally expected, including the 530MW Stockyard Hill wind farm which will overtake Coopers Creek as the biggest in the country when it finally gets on line. Coopers Gap has been running about one year behind its original schedule.

PARF has also been having problems with the Broken Hill solar farm and the Silverton wind farm, both of which have been impacted by grid constraints in western NSW, and have been warned of further problems in coming years because of congestion on the main transmission line that connects them to the grid.

The 420MW Macarthur wind farm operated by AGL delivered a relatively low capacity factor of just 26 per cent last year.

 

 

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Peter Dutton’s nuclear accounting trick #4: Assume climate change has no cost

What is omitted from the Coalition's nuclear policy costings is far more informative about the…

23 February 2025

Akaysha inks revenue swap deal for Queensland big battery with commodities trader

Akaysha Energy signs "sophisticated" revenue swap deal for its new Queensland big battery with a…

21 February 2025

Mount Isa turns to wind, solar and gravity storage to save city as big mines close

Mount Isa is looking to green energy and gravity storage in its disused mine shafts…

21 February 2025

Energy Insiders Podcast: Why is the green energy transition made to sound so hard?

Climate 200's Simon Holmes a Court on the upcoming election, the role of independents, lessons…

21 February 2025

Peter Dutton’s nuclear accounting trick #3: Hide the costs of keeping coal

The Coalition’s nuclear plan takes a gamble with our electricity system that old coal will…

21 February 2025

Indigenous-owned energy retailer branches further across NEM, supplies power to NBN

Australia's first Indigenous-owned energy retailer is expanding into two more states just eight months after…

21 February 2025