Australia’s biggest solar and battery hybrid project planned at site of abandoned “dud” coal mine

Published by

The site of a controversial coal mine – originally designed to support a new coal fired power station in NSW – is to be developed into what will surely be biggest co-located solar and battery storage hybrid projects in Australia’s main grid.

Pacific Partnerships, part of the listed engineering and construction company Cimic, announced on Tuesday that it will build a 700 megawatt (MW) of solar and up to 1,600 megawatt hours (MWh) of battery storage at Cobbora, where the state government had a decade ago planned a new coal mining project before abandoning the controversial proposal.

The plan for the Cobbora coal mine, near Dunedoo in the state’s central west, included a proposal for a new coal fired generator and was described as the “dud deal of the century” in 2014 by the then treasurer Mike Baird.

The land parcels for the coal project were sold by the state government and the solar and battery project in its place was first proposed by Sydney-based renewable energy developer Marble Energy.

The rights to that project have now been bought by Pacific Partnerships, which has massively upsized the battery component from an original 200 MW and 200 MWh. It will develop the project and hire its sister company UGL to build and operate it.

“Cimic is committed to Australia’s energy transition and is developing the large-scale renewable generation assets and infrastructure required to support it,” group chairman Juan Santamaria said in a statement.

“NSW is part of our strategic new energy focus as we expand our diversified national portfolio of assets and contribute to the Australian Government’s commitments to reach net zero emissions by 2050.”

The Cobbora project is located within the Central West Orana Renewable Energy Zone (CWO REZ), which is a key part of the NSW government roadmap to replace its ageing coal fired power stations with renewables and storage.

Source: Marble Energy.

The project is located 55km east of Dubbo on mostly cleared grazing land and is expected to continue to host sheep grazing when the solar farm is operational.

It will be Cimic’s second big solar project, following the newly completed Glenrown solar farm in Victoria, and the company says it plans to repeat the benefit sharing program with the local community from the project.

An Environmental Impact Statement for Cobbora is due to be submitted to the NSW Department of Planning and Environment (DPE) in late 2024, before being placed on public exhibition for community and stakeholder feedback.

“The Cobbora Solar Farm will be located on a low, undulating landscape. This makes it an ideal site for a solar farm development,” Marble Energy co-director Tim Kirk said in a statement.

See also Renew Economy’s Big Battery Storage Map of Australia.

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Solar Insiders Podcast: Why new rules for networks signal a new dawn for consumers

AEMC commissioner Rainer Korte on what the new rules on reporting and data sharing will…

17 July 2026

Developer lands “complete funding package” to begin building state’s largest solar-battery hybrid

Developer says it is good to go on early works and construction of the largest…

17 July 2026

“A really big game-changer:” AEMO looks to battery inverters as syncons prove expensive and hard to find

AEMO says proof that grid forming battery inverters can deliver heartbeat of the grid will…

17 July 2026

Twiggy Forrest’s Squadron abandons plan for troubled New England wind farm

Days after lodging new plans for a more than 500 MW wind farm, Squadron dumps…

17 July 2026

Energy Insiders Podcast: Is Australia on target for a “step change” in energy?

AEMO’S head of systems Nicola Falcon on the 2026 ISP and the importance of grid…

17 July 2026

Australia’s solar PV recycling plans on hold after flagship pilot project suspended

Flagship pilot program to set up 100 sites around the country to collect used solar…

17 July 2026