Ark Energy scales back huge Queensland wind farm to avoid ecological sites

Published by

A massive wind farm proposed for construction in Queensland’s Tablelands region has been whittled back to less than half its original size, after 114 of the 200 turbines initially proposed were cut to avoid sensitive ecological and cultural heritage sites.

Project developer Ark Energy – part of the massive Korea Zinc group – said on Thursday that the wind farm will still have a maximum generation capacity of 602MW, which is slightly higher than originally planned, despite the reduction in turbine numbers.

In a new Public Environment Report, put forward for assessment by the federal government, Ark says this output will be achieved with up to 86 wind turbines – down from 95 proposed last year, which had already been halve from 200 proposed initially.

The wind turbines will be sized between 5MW-7MW and the project will include associated infrastructure, including potentially battery storage.

The changes come after concerns were raised over the development’s potential environmental impacts, given its location close to national parks that form part of the Wet Tropics of Queensland World Heritage Area.

The project, which came into Ark Energy’s hands via its purchase of Epuron in December of 2021, was last year determined to be a “controlled action” under the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).

This gives the federal government power of veto – or approval – of the project, according to an assessment of its impact and ability to deliver a “net positive outcome” for biodiversity over the longer term.

Ark Energy says the most recent design change to the project removed a further eight wind turbines, resulting in a reduction of access roads by 27km, and a sub-station relocation that has cut overhead transmission lines by 4km.

The final proposal also makes an “industry-first” commitment to rehabilitate at least 70% of the construction disturbance and strategic land-based offsets within the project area, totalling seven times the construction footprint.

The rehabilitation program aims to be conducted in collaboration with local land care groups and to incorporate Indigenous training and employment.

“Over the course of the project’s planning and assessment phase a total of 114 wind turbines from an initial layout of 200 have been removed to address concerns and reduce impacts,” a statement on the project website says.

“The project is now less than half its original size. It completely avoids all rainforest and the nearest disturbance to the western boundary of the Wet Tropics of Queensland World Heritage Area is 600 m in only one location and otherwise almost 1 km or more.”

Ark Energy’s general manager for development in Queensland, Anthony Russo, says the final proposal is the result of two years of ecological assessment work and intensive consultation with a range of stakeholders including ecologists, Traditional Owners, and the local community.

“Increasing renewable energy supply is urgent to reduce carbon emissions, replace fossil fuel energy sources and meet growing electricity demand,” Russo says.

“Conserving the natural environment and Australia’s unique biodiversity is equally important. Achieving these priorities together… requires robust science, an interdisciplinary approach, and careful planning and management.”

Russo says the project area for Chalumbin wind farm was chosen for its “excellent” wind resource and high voltage transmission lines with capacity, making it imperative to strike a balance between the project’s renewables benefits and its unavoidable impacts.

“In addition to industry-leading community benefit funding, hundreds of jobs and millions in economic activity, this proposal provides conservation benefits for key species and a path to achieve a significant net gain for biodiversity in the project area over the longer term,” he says.

The project’s draft Public Environment Report is now on public exhibition until December 16.

(This story has been updated to clarify reductions in turbine numbers and size of proposed turbines).

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Energy Insiders: Grid scale sodium batteries are on their way

The battery industry is about to witness another change in chemistry and technology. Valo Energy…

16 October 2026

“Just a fantasy:” Energy minister slams Opposition gas and nuclear ideas, vows to hold the line on renewables

Energy minister says imminent closure of coal is "indisputable," and "ideology-driven" policies to scrap transmission…

16 October 2026

Supplier to Australia’s biggest battery expects to announce first sodium-ion battery project soon

The supplier to the biggest battery currently being built in Australia expects to announce its…

16 October 2026

Wind projects will need help “for a while”, says new green bank boss in shift of funding priorities

The federal government green bank has dusted off an old mandate, but has not ruled…

16 October 2026

Anti-renewables groups still spending big on Meta – and met with near silence by green energy industry

Fossil fuel interests spent $1.2 million on Meta ads in the last three months, a…

16 October 2026

Australia can still become a giga-scale solar manufacturer, says Arena, as it flags new local PV maker

Australian Renewable Energy Agency says the country can still become a major solar PV manufacturer,…

16 October 2026