Wind

All 31 turbines completed at 110MW Biala wind farm in NSW

Published by

Developer BJCE Australia (Beijing Jingneng Clean Energy Australia) said in a newsletter update this week that 10 of the project’s completed Goldwind turbines are generating electricity already at the site, while a further 17 are ready to power up, and commissioning is underway for another 14.

Progress has been steady on the wind farm, despite a year of major disruption. As RenewEconomy reported, Goldwind turbine components started making the 233km trip from Port Kembla to the site 8km east of the township of Biala in the mid-march, just as Australian state governments were moving to close borders and implement other strict measures to limit the spread of Covid-19.

The completion of the project’s first turbine was celebrated on LinkedIn in April. At the time, BJCE Australia’s deputy general manager Derek Powell told RenewEconomy that the company was upbeat about the large-scale renewable energy prospects of Australia.

“We own and operate our own assets, so we’re in for the long haul. And we think there’s a good outlook in Australia,” he said.

In a LinkedIn post this week, Goldwind Australia, which has partnered with BJCE on the Biala project, gave a shout-out to customers, industry and project partners, local communities, and employees for helping to deliver significant projects across the nation.

“Despite a challenging year, we have achieved some major milestones and we thank you for sharing and celebrating these moments with us,” Goldwind Australia said.

The Biala wind farm is expected to produce enough electricity for approximately 46,000 typical homes on an average day of wind, once it reaches full generation capacity.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Administrators call time on Whyalla Steelworks’ coal furnace “delusion,” hundreds of jobs to go

Administrators of Whyalla Steelworks abandon efforts to reboot the plant's coal-fired blast furnace, wiping out…

14 September 2026

UK group snaps up leading wind, solar and battery consultancy as part of Australian buying spree

UK-based asset management group buys prominent Melbourne consultancy specialising in wind and solar developments as…

14 September 2026

New wind and battery energy park, backed by super funds, proposed for south-east Queensland

Another wind and battery project proposed for south-east Queensland, despite pushback by state government and…

14 September 2026

Former Liberal leader appointed to Snowy Hydro board as market awaits another Snowy 2.0 reset

Former Liberal leader and ex AEMO system design boss appointed to Snowy Hydro board as…

14 September 2026

Should ageing coal generators be fed carrots or sticks? | Energy Insiders

Smart Energy Council CEO David McElrea on LNP ideology, how to close coal fired generators,…

14 September 2026

“Incredibly ambitious”: Electricity market reforms given express track by energy ministers

Plan by energy ministers to agree on the new design for the National Electricity Market…

14 September 2026