Developer BJCE Australia (Beijing Jingneng Clean Energy Australia) said in a newsletter update this week that 10 of the project’s completed Goldwind turbines are generating electricity already at the site, while a further 17 are ready to power up, and commissioning is underway for another 14.

Progress has been steady on the wind farm, despite a year of major disruption. As RenewEconomy reported, Goldwind turbine components started making the 233km trip from Port Kembla to the site 8km east of the township of Biala in the mid-march, just as Australian state governments were moving to close borders and implement other strict measures to limit the spread of Covid-19.

The completion of the project’s first turbine was celebrated on LinkedIn in April. At the time, BJCE Australia’s deputy general manager Derek Powell told RenewEconomy that the company was upbeat about the large-scale renewable energy prospects of Australia.

“We own and operate our own assets, so we’re in for the long haul. And we think there’s a good outlook in Australia,” he said.

In a LinkedIn post this week, Goldwind Australia, which has partnered with BJCE on the Biala project, gave a shout-out to customers, industry and project partners, local communities, and employees for helping to deliver significant projects across the nation.

“Despite a challenging year, we have achieved some major milestones and we thank you for sharing and celebrating these moments with us,” Goldwind Australia said.

The Biala wind farm is expected to produce enough electricity for approximately 46,000 typical homes on an average day of wind, once it reaches full generation capacity.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Home battery installations will match the scale of Snowy Hydro scheme – in a single year

Household battery numbers continue to defy all predictions, and they now look set to match…

16 January 2026

“Too valuable to throw out:” Labor announces first national solar panel recycling pilot program

Federal government announces $25 million for a rooftop solar recycling pilot, with up to 100…

16 January 2026

Fortescue begins work on first wind farm, with self-lifting towers and Australia’s biggest turbines

Andrew Forrest's Fortescue starts construction of its first wind farm, featuring unique "self-lifting" tower technology…

16 January 2026

Standalone battery proposed for old gravel pit gets final planning tick despite long distance objectors

A $200 million standalone battery project that attracted no objections from within 50kms of the…

16 January 2026

Australia’s climate hit regions will need fit-for-future science and modelling

It won’t come as much consolation to Victorian communities picking through the burnt rubble from…

16 January 2026

One ship loaded with solar PV is now worth more to the grid than 120 coal-carriers

Technology gains mean that one ship load of solar PV panels is now worth more…

16 January 2026