Alinta plans big solar farm and four hour battery in Port Hedland grid play

Published by

Energy utility Alinta has unveiled plans for a 90MW solar farm and a four-hour big battery near Port Hedland in Western Australia, part of a major new power play that will set new benchmarks for solar and battery storage   in Australia.

The plans are for a 90MW solar farm near Port Hedland and a 30MW/120MWh big battery adjoining the existing gas generator in the same area, and both will be the largest of their type away from a major grid in Australia, and the battery may end up being the first four-hour installation in the country.

The plan, first unveiled by Alinta at the Pilbara 2021 regional conference last week, heralds the rapid growth of renewables and storage in the major mining region in the remote north-west, an area that until a few years ago saw little alternative to their complete dependence on expensive and heavily polluting fossil fuels.

Alinta has already built a hugely successful big battery at Mt Newman, and is just completing the finishing touches to its 60MW Chichester solar farm (pictured above) that will help power the huge mining operations of  Andrew Forrest’s Fortescue iron ore group.

Fortescue is also looking to add large scale solar and big batteries at its new mines, as are Rio Tinto and BHP and even Gina Rinehart’s Roy Hill at their respective mining operations. The miners’ plans go well beyond just providing power for mine sites, however, with Fortescue and others looking for massive multi-gigawatt scale projects for renewable hydrogen.

Alinta’s strategy at Port Hedland is to use the new solar farm and the four-hour big battery to respond to demand from its corporate customers for cleaner energy.

“Corporates in Australia are looking for low carbon power solutions, and are looking to the market to provide them,” Alinta’s head of strategy Gary Bryant told RenewEconomy in an interview.

Alinta operates a discreet network within a bigger grid operated by Horizon Energy that supplies customers in and around Port Hedland. The 90MW solar farm will provide up to 100 per cent of its customers needs during the day, while the battery will be used to time-shift excess solar into the evening.

That’s the main difference between the Mt Newman battery, which at 35MW/12MWh deliberately has just 20 minutes storage because its principal role is to allow Alinta to switch off the gas generators normally used to back up the operating gas turbines (yes, even fossil fuel generators need back up).

The Port Hedland battery will have up to four hours storage to store excess solar, and also to allow the Port Hedland gas turbines to be operated at full capacity in the evening. These will charge the battery, which can then be discharged once or twice during the night, before repeating the process during the day.

Bryant says this will deliver significant fuel and carbon savings from the operation of the gas generators, because operating the turbines at full rather than partial capacity delivers increased efficiency.

But Alinta is also looking to add wind energy to provide clean power overnight. It is currently looking at four or five locations for a potential wind farm in the region, also with an eye to the considerable increase in electricity demand expected from the switch to electric transport and the creation of renewable hydrogen hubs.

“Solar is very predictable, but wind energy is the key to getting costs down,” Bryant said. “Time shifting energy through a battery does come to a cost, and the cost of wind is less than solar and a battery.”

But Bryant also says that while four-hour storage is not economic yet on Australia’s main grid, the combination of solar and battery storage is competitive with the gas generation on grids in the country’s remote north-west.

“We want the battery to time shift solar – from the daytime to the night-time. When the battery runs down to a lower state of charge we can run the gas turbines at full load and charge the battery. That saves carbon because it is more efficient.”

Bryant says Alinta is currently favouring a 30MW battery with four hours storage (120MWh), but depending on what suppliers suggest it could change this to 70MW with two hours, or even 70MW with four hours storage.

Environmental approvals have already been submitted for an upgrade to the Port Hedland gas generator, with the idea of building more fast-start reciprocating engines that are more flexible, but this may not be built out to capacity due to the added idea of solar and a big battery.

Another potential development is the increased connection between the four distinct networks in the North West Interconnected System that are operated by Horizon (Port Hedland to Karratha), Alinta (to mining customers), Rio Tinto, and the new one to be built by Fortescue, with its own solar and big batteries.

 

Bryant says this will boost resilience and the amount of renewables that can be comfortably accommodated within the grid. Right now, he says that a 50-60 per cent share is not difficult with battery storage, and up to 80 per cent is also possible, with the support of other network “devices”.

Beyond that, the question of back up storage for rare events becomes a major cost. “Above 80%, storage comes an issue, and the cost of storage becomes an issue. You can get to 100% tomorrow if you didn’t worry about what to pay for it.”

See RenewEconomy’s big battery storage map: Big Battery Storage Map of Australia

Have you completed RenewEconomy’s short reader survey yet? With feedback from readers like yourself, we can keep improving and growing. Please click here to start the survey.

 

 

 

 

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Offshore wind project wins court appeal over rejected licence in Gippsland

One of Australia's first offshore wind projects has been given a lifeline after a court…

8 November 2024

10 reasons why Donald Trump can’t derail global climate action

Now is a good time to remember that efforts to tackle the global climate crisis…

8 November 2024

“HOFF and HON:” Gold mine passes key test, shifts to 100 pct renewables and back again

Remote mine microgrid transitions from hydrocarbons off (HOFF) to hydrocarbons on (HON), demonstrating its ability…

8 November 2024

Alinta signs early contractor deal for first multi-billion dollar pumped hydro project

Alinta signs early contracting deal for proposed multi-billion dollar pumped hybrid project in NSW.

8 November 2024

Land deal signed for deep storage to create Broken Hill mini grid, but network rules still stand in the way

Land deal signed for long duration compressed air storage facility at Broken Hill that the…

8 November 2024

Energy Insiders Podcast: Trump is back, and the frog is still boiling

Donald Trump is back. Richie Merzian from the CEIG joins the podcast to discuss the…

8 November 2024