Australia’s biggest coal generator AGL Energy is seeking a federal green tick for a two-hour big battery project it proposes to build adjacent to an existing substation in the heart of New South Wales coal country – its third big battery in the Hunter Valley.

The proposed Beresfield battery energy storage system (BESS) is proposed for an industrial area in Newcastle and will have a total capacity of up to 170 megawatts (MW) and 340 megawatt‑hours (MWh) of usable storage capacity.

It joins the queue with NSW state development approval already locked in, having been secured back in early 2024 by the project’s original developer, Firm Power. AGL bought Firm Power and its pipeline of six battery projects in August of 2024.

Impressively, Firm managed to get the Beresfield BESS through the notoriously slow and costly NSW development approval process in just six months, at the time citing the benefits of an improved process from the NSW Department of Planning and Environment (DPE).

AGL has been rapidly growing its battery storage portfolio – both big and small – and is betting on BESS as a major cash cow for the company in the transition to renewables and flexible capacity.

It is building the 500 MW, 1,000 MWh Liddell battery further up the valley at the site of the now shuttered coal fired power station, and has also committed to a 500 MW, 2,000 MWh closer to Newcastle at Tomago.

At the company’s annual results presentation in August, CEO Damien Nicks and chief financial officer Gary Brown made it clear that the company’s focus – like those of the other major utilities Origin Energy and EnergyAustralia – is on storage rather than wind and solar.

In the referral documents for the Beresfield BESS, AGL says the proposed project area and disturbance footprint have a “significant disturbance history” associated with historical industrial land use.

Hunter Wetlands National Park is located 2.5 km to the south-east of the proposed site, but is separated from it by light industrial land uses, the New England Highway and John Renshaw Drive, the documents say.

“Due to the mixture of land uses in the immediate area, the disturbance footprint has no connectivity with vegetation in adjoining lands,” the referral says.

It now remains to be seen how quickly the project can make its way through the federal EPBC Act.

If you wish to support independent media, and accurate information, please consider making a one off donation or becoming a regular supporter of Renew Economy. Your support is invaluable.





Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Delays at Australia’s most powerful battery lead to a more than $90 million cut in payments

Regulator quantifies the revenue cuts caused by the delayed start of the giant shock absorber"…

30 May 2026

Huge six-hour battery gets federal green tick for grid sweet-spot at edge of coal hub

Plans to install a big battery with up to six hours storage in a sweet…

29 May 2026

State locks in six renewable energy zones after final round of nips, tucks and rethinks

State formally declares five onshore renewable energy zones and one “shoreline” REZ, to guide its…

29 May 2026

Lower emissions, lower prices, and new investment: It’s been a good week for Labor’s green energy plan

A cut in emissions led by more renewables, batteries and EVs, and less coal, lower…

29 May 2026

Energy Insiders Podcast: Plugging the holes in EV charging

Jet Charge founder Tim Washington on the need for more chargers, faster machines, multiple bays…

29 May 2026

Big batteries scoop the pool in grid firming tender that was also open to gas generators

Big batteries scoop the pool and sideline gas in "firming tender" designed to secure supply…

29 May 2026