AGL says infrasound levels unchanged by Australia’s largest wind farm

Published by

An independent investigation into the noise generated by Australia’s largest wind farm – the 420MW Macarthur Wind Farm in South West Victoria, jointly owned by AGL Energy and Malakoff Corporation Berhad – has found that infrasound levels at the site have not changed since the construction of the project’s 104 turbines.

The research – which was voluntarily commissioned by AGL and conducted by Resonate Acoustics – measured both infrasound and low frequency noise at residences located between 2.7-1.8 kilometres from the nearest turbine. It did this before any turbines were operating, when approximately 105 of 140 turbines were operating, and when all 140 turbines were operating.

The results, which have also been reviewed by internationally renowned low frequency acoustic expert Dr Geoff Leventhall, show no measurable change in the infrasound levels measured before and after construction of the project.

“AGL has undertaken the most extensive and rigorous research by a wind farm operator in Australia and also has gone above and beyond its regulatory requirements,” said AGL’s general manager of power development, Scott Thomas.

Thomas also acknowledged the cooperation of local residents during the “intrusive” internal noise monitoring process, which involved equipment being placed within household bedrooms facing the wind farm during each stage of monitoring.

The equipment stored G-weighted sound pressure levels and linear sound pressure levels to enable assessment of the infrasound and low frequency noise levels. The study compared the baseline or pre-operational data and the operational levels after construction over a combined measurement period of 90-plus days.

Measured infrasound and low frequency noise levels were also assessed against best practice international and Australian guidelines.

As well as infrasound monitoring, AGL undertook noise monitoring at 25 neighbouring properties between October 2012 and May 2013, since the first operation of a wind turbine at Macarthur Wind Farm, to ensure that the wind farm complied with noise regulations.

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Share
Published by

Recent Posts

Electrochemical “bath” could bring spent lithium-ion batteries back to life, cut cost of recycling in half

Researchers believe they have found a way to recover almost the full life of lithium-ion…

2 July 2026

Thin white strips on brown slopes: Manufactured ski seasons are fuelling the climate problem

Ribbons of manufactured snow remind us that national parks should be front-line responses to climate…

2 July 2026

Giant remote zinc mine aims to reach at least 80 pct renewables with addition of wind farm and big battery

One of the world's largest zinc mines, in remote north-west Queensland, will be run with…

2 July 2026

New $50 million federal fund to slash energy use, build climate resilience at local sport clubs

Game On: A new $50m federal government funding pool will provide one-off grants to up…

1 July 2026

Virtual networks and the real pursuit of energy democracy | Solar Insiders

Deakin University’s Andrea La Nauze on the early findings from an Australia-first trial of technology…

1 July 2026

Plan to power off-grid data centre with solar, gas and a 16 gigawatt-hour battery seek federal green tick

Project Ares wants to build a 1 GW data centre on a cattle station on…

1 July 2026