Broken Hill is about to get a 50MW big battery to support wind and solar

Published by

AGL has won planning approval for a new 50MW, two-hour battery in Broken Hill, to support its wind and solar farms in the area, as it continues its plan to roll out nearly one gigawatt of battery storage across the main grid.

The Broken Hill battery this week won planning approval from the NSW Department of Planning, Industry and Environment (DPIE) and AGL says it will help improve the reliability of the energy supply in the historic mining centre.

AGL developed the 200MW Silverton wind farm and the 53MW Broken Hill solar farm which are now owned by the PowAR fund, in which AGL holds a 20 per cent stake, but these are often severely constrained by the congestion on the main transmission links.

A final investment decision is expected later this year. AGL says it will depend on contracts, and insists it will be made independently of other projects in the region, although it does seems clear they will impact the dynamics of the local market.

Network company Transgrid is working on two major projects at the moment, a possible Broken Hill micro-grid to replace two existing diesel generators in the town, which could include the world’s biggest compressed air storage facility, a 200MW project with up to eight hours storage that would use underground caverns.

A final report on that and competing proposals – including, ironically, refurbishing or replacing the ageing diesel generators – is to be handed to regulators soon.

Meanwhile, Transgrid has also delivered its latest assessment of the best options to relieve congestion in other areas of the state – a situation that has impacted multiple solar farms and the PowAR assets in the past – favouring a new high voltage link from Darlington to Dinawan.

That report also investigated battery storage and Statcom options, but decided that a new 330kV line – joining into Project EnergyConnect and Transgrid’s proposed 2.5GW Dinawan renewable energy hub, would be the best option.

AGL’s Broken Hill battery battery will be located on industrial land, near the Broken Hill substation and around 6km southeast of the local airport and, if a final investment is made, construction will start later this year and be commissioned in 2023.

“AGL’s grid-scale battery projects are ensuring we have energy storage and firming capacity at the ready to enable a seamless transition from thermal generation to renewables,” AGL chief operating officer said in a statement.

“The limiting factor for renewable technology has always been storage but we are taking control of these constraints by turning our attention to firming technology, like batteries.”

Broken Hill is one of a number of battery storage projects being built or contracted by AGL, including the 250MW battery at Torrens Island in South Australia, which will be built initially with one hour storage before being expanded to up to four hours storage.

That battery will be the first in Australia to use “grid forming inverters” at such a scale. AGL is also mulling big battery projects at the sites of its Loy Yang coal generator in Victoria and Liddell in NSW.

It is also contracted to take the output of the nearly complete 100MW/150MWh Wandoan battery in Queensland, which has started commissioning, and has a contract with Maoneng to build 200MW/400MWh of battery storage, likely at the Sunraysia solar farm and at Lismore.

“Batteries and energy storage are critical to supporting the increased growth of renewable generation and in turn driving downward pressure on wholesale electricity prices,” Brokhof said.

“During construction, we expect the project to create up to 50 direct jobs, providing direct financial benefits to local businesses and the wider community.”

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s battery revolution is pushing gas out of the grid support business

Australia's most isolated grid is showing the world how the net zero transition will put…

11 December 2025

Gas pipeline giant proposes new solar, wind and battery hub for Pilbara

APA wants to build a "large" wind, solar and battery hub deep in the Pilbara…

11 December 2025

Aussie tech could give second life to turbine blades in high-tech medical, agri uses

Pacific Blue has funded two research projects to see if Australia-made tech can reuse fibreglass…

11 December 2025

Origin to “significantly extend” storage capacity of Australia’s biggest battery, to cover evening demand peak

Origin approves expansion of what will already be the biggest battery in Australia as it…

11 December 2025

Solar Insiders Podcast: Big trouble in the small-scale battery rebate

Smart Energy Council's David McElrea on why federal Labor must make some urgent changes to…

11 December 2025

Queensland LNP dumps renewable targets, but can it teach coal plants to dance around solar?

Queensland LNP officially scraps state renewables targets, on the belief it can keep its coal…

11 December 2025