Renewables

AEMO says wind, solar and storage pipeline at record high, as battery proposals double

Published by

The Australian Energy Market Operator says the capacity of wind, solar and battery storage projects queuing for connection in Australia’s main grid has jumped to a record high over the last year, increasing by more than a third to more than 50 gigawatts for the first time.

The increase has been driven by battery storage project proposals, which have nearly doubled from 11 GW to 20.5 GW since the same time a year ago.

Solar and battery hybrids have grown from 4.5 GW to 5.6 GW, wind projects from 7.5 GW to 8.7 GW, and solar only projects from 10.2 GW to 12.1 GW. The total in the queue is now 51 GW.

These figures represent the capacity of projects working through the application process for connection to the grid. There are many more in earlier stages of development.

“It’s a new record of renewable and firming projects working to connect to the National Electricity Market,” said AEMO’s head of onboarding and connections Margarida Pimentel.

There are also, according to AEMO, seven projects totalling 1.7 GW that received application approvals, seven more than were registered (2.4 GW) and five projects that reached full output: Blyth Bess (pictured above), Gangarri Solar Farm (150 MW), Crookwell 3 Wind Farm (56 MW), Mokoan Solar Farm (46 MW) and Kingaroy Solar Farm (40 MW).

Australia has a target of 82 per cent renewables by 2030, but is currently sitting at just over 40 per cent. It needs to get a wriggle on to reach its target – which happens to coincide with the modelling in AEMO’s Integrated System Plan – and the speed of planning, connections, construction and new transmission will be key.

Battery storage has been the sweet spot for developers in the past year, thanks both to their falling costs, their modular nature, and their construction simplicity – although the commissioning process has and remains challenging for some, particularly those contractors new to the country.

Apart from the doubling of battery storage project applying for a connection, many of the project alterations include proposals to add batteries to previously approved projects, both in planning and in commissioning.

Pimentel says NSW is host to the most capacity, followed by Queensland, Victoria and South Australia. Tasmania accounts for just 0.25 per cent of the new capacity.

She says that 16 projects totalling 2.5 GW in capacity have reached full output in the current financial year, which sounds less than what is required to meet the 2030 target, and is barely changed from last financial year.

However, projects underwritten in the new Capacity Investment Scheme auctions could hurry along that process, although energy analysts note that more capacity backed in the CIS will be needed to meet that target.

Pimentel says work is continuing to try and accelerate the connections pipeline – a challenge 

 


Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Australia’s first offshore wind auction set for August after nearly one year delay

Victoria sets new date for its first offshore wind tender, nearly a year after the…

27 January 2026

French giants dominate offshore wind licences out west, but none offered in Illawarra or Bass Strait

Three projects totalling up to 4 gigawatts offered feasibility licences in W.A., but the Illawarra…

26 January 2026

New $20 million “Made Right Here” ad campaign kicks off at low-carbon aluminium maker in NSW

A $20 million national ad campaign raising awareness of Australian-made products kicked off late last…

26 January 2026

Buyer Beware: Carbon credit platforms repeating ills of the past

Claims and promises of carbon offset schemes are falling deep into the category of being…

23 January 2026

“Total transformation of the Australian summer:” Climate change made January heatwaves five times more likely

Australia has just experienced its worst heatwave in six years but it's set to become…

23 January 2026

Shared solar: Labor’s “free power” plan to have daily cap to stop abuse by EV and home battery owners

There will be daily cap on the federal government's Shared Solar free power offer, to…

23 January 2026