Policy & Planning

AEMO reports surge in grid registrations for wind, solar and battery projects

Published by

The rate of grid registrations for wind, solar and battery projects has surged in the last six months, with the capacity of projects given the go-ahead to connect to the grid double that of the previous 12 months.

New data released by the Australian Energy Market Operator shows that with 1.7 gigawatts (GW`) of new projects were registered in the December quarter, taking the total since July 1 to 5.2 GW – more than double the previous 12 months.

Margarida Pimentel, the head of AEMO’s onboarding and connections group, says the big increase in projects that have been built and can now move through the commissioning process reflects the “wave” of application approvals in 2023.

That wave continues, with another 7.5 GW of project application approvals over the past six months, similar to the same period in 2023. The rate increased in the last quarter, with 4.9 GW of new project application approvals.

And, as previously reported on Renew Economy, the number of projects progressing through the connection process now stands at 49.6 GW , up from 36.4 GW at the end of 2023.

Source: AEMO.

“Given the NEM’s (National Electricity Market) total generation and storage capacity of 66 GW, nearly 50 GW of new projects marks a significant pipeline of future energy supply,” Pimentel said in a statement.

The capacity of projects reaching full output, and finishing what can sometimes be a lengthy commissioning process, also reached 2.2 GW in the latest six months, equivalent to the capacity completed in the previous 12 months.

Those projects reaching full output included the 205 MW Ryan Corner wind farm, the 76 MW Girgarre solar farm, the 200 MW, 400 MWh Rangebank battery in Victoria (pictured at top) – all in Victoria – and the much delayed Tailem Bend hybrid facility (combining a second stage solar farm with a 49 MW/MWh battery) in South Australia.

The numbers released in the latest AEMO Connections Scorecard will be seen as validation of both AEMO’s Integrated System Plan and the federal government’s energy policies, although it remains to be seen if the country can roll out new projects quickly enough to meet the target of 82 per cent renewables by 2032.

The federal government is also contracting record numbers of new projects through its series of auction under the Capacity Investment Scheme. More than 6GW of new wind and solar capacity was awarded in the first auction completed in December, while a second auction is now underway.

Grid capacity, and the delays and cost overruns of key transmission projects, remain the biggest – although not the only – hurdle.

In the latest period, AEMO says solar projects led registration approvals in the December quarter with a total of 831 megawatts (MW), followed by wind (440 MW), batteries (350 MW), and upgrades to existing facilities (49 MW).

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

New Australian developer targets big batteries with four projects in NSW and Victoria

A newly formed Australian renewables and storage developer has unveiled its first four battery projects…

20 March 2025

“Not the right fit:” Community fractured as local council votes to oppose big battery project

Local community is divided over a big battery project in north-east Victoria, and the council…

20 March 2025

“We will not back down:” Court tells Greenpeace to pay billion dollar damages bill to oil and gas company

Billion dollar finding against Greenpeace has implications for green groups in Australia who are also…

20 March 2025

Time for AEMO to get real and stop ringing the alarm bell on gas shortages

AEMO has again downgraded its gas forecasts as consumers choose electrification given the price gouging…

20 March 2025

Iconic fossil fuel smokestacks are being taken down one brick at a time

An old power plant south of Perth is slowly being taken apart, with the chimneys…

20 March 2025

Fewer, bigger turbines proposed as huge green hydrogen project wins first federal head-start funding

Plans to install up to 6GW of wind and solar to produce green ammonia in…

20 March 2025