Storage

AEMO provides connection approval for another two grid-forming big batteries

Published by

Renewable and battery storage developer Ace Power says it has received connection agreements with the Australian Energy Market Operator for two new grid forming big battery projects, one in Victoria and another in north Queensland.

The approvals have been given to the 103 MW, two hour Kerang battery in Victoria, and to the 200 MW, two hour Yabulu battery north of Townsville. Both will connect to the network near existing sub-stations and close to neighbouring solar projects, the planned Kerang solar farm and the planned Yabulu solar project.

Senior Development Manager & BESS Lead, Shane Humphreys, said ACE Power was delighted with the outcome.

“We are very proud as ACE Power to have achieved our first two 5.3.4A&B approvals from AEMO in close succession,” said Shane Humphreys, the senior development manager and battery storage lead at Ace Power.

“These are among the earliest approvals nationwide for BESS to operate in grid forming mode from the date of commissioning. This outcome is the culmination of over 12 months work, and considerable engineering input from our respective consultants as we navigated an evolving landscape in respect of how grid forming inverter technology is assessed by AEMO and the NSPs.”

Humphreys says that both projects will operate in grid forming mode which will contribute positively to network stability on a 24/7 basis by providing some of the critical grid services – such as inertia and system strength – traditionally provided by coal and gas generators.

This, in turn, is expected to unlock further capacity for renewable connections in their surrounding areas.

Humphreys says the company hopes to start construction on both projects within the next six months.

See also: RenewEconomy’s Big Battery Storage Map of Australia

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

Off with the blades: Pioneering community-owned wind farm has first major component repair

Australia's first community owned wind farm has blades and rotor removed to undergo its first…

25 March 2026

New solar farm built in Australia’s most destructive wind area “didn’t miss a beat” in recent cyclone

Newly completed solar farm quickly put to the test in the only region rates with…

25 March 2026

State unveils its own “solar sharer” offer, promises bill savings of up to $1,000 a year

State confirms it will roll out its own version of the federal Solar Sharer offer,…

25 March 2026

How a robot named Bear is making solar farm maintenance safer and more efficient

Autonomous robots originally designed for the mining industry are being programmed to track across thousands…

25 March 2026

Big battery and CIS contract-winner seeks federal green tick for construction

A CIS-winning big battery is now seeking a green tick ahead of a possible start…

25 March 2026

Fire at wind farm claims lives of workers inspecting turbine tower

Reports claim three workers have died at a 20-year-old wind farm in South Korea after…

24 March 2026