Collgar wind farm
The Australian Energy Market Operator has furthered its push for major and rapid reform in the West Australian electricity grid, citing events on the Good Friday holiday that it said were so challenging it has dubbed the day as “Bad Friday.”
A presentation was made by AEMO officials in Perth recently, highlighting the volatility from both the state’s growing rooftop solar capacity (now nominally the largest generator in the local grid), and its increasing amount of wind power.
In most grids, AEMO has argued, the current penetration of wind and solar that exists in W.A. may not be much of a problem. But because WA’s South West Interconnected System (SWIS) is isolated, and the archaic rules make many of the obvious solutions difficult to obtain, the operator is faced with growing problems.
It has warned that wholesale reform is required, and the state has responded by instigating a whole of system inquiry to go along side a distributed energy roadmap to try to manage and harness the growing amount of rooftop solar and distributed storage.
The “Bad Friday” presentation made to the WA Electricity Consultative Forum in late June was designed to reinforce how timely these investigations need to be, because of the challenges presented as a big front passed over in the early morning, accompanied by gusty winds up to 90kmh caused wind output to also swing dramatically and then clouds that caused rooftop solar output to also vary wildly.
The wind output looked like this.
And this was the output (see below) from rooftop solar, with great volatility as the clouds came over. This situation is likely to intensify as the amount of rooftop solar doubles, or even triples, in the next 10 years.
This in turn had an effect on demand.
Sabiene Heindl from The Energy Charter on the need for strong regional leaders for transition…
Big battery developers are facing increasing scrutiny from local communities about their projects. Some of…
Record levels of solar, wind and battery use are pushing down emissions in Australia but…
As the NT government fights to power future data centres with gas, its publicly-owned utility…
Bowen says transmission projects are key, including the VNI West link now under threat from…
Nine north-western Victoria councils are fighting to ensure their communities get the most out the…