Markets

AEMC snaps to attention on interconnector, fast-tracks rule change

Published by

The push to fast-track approval of a new high capacity electricity interconnector between South Australia and New South Wales has reached all the way to the top, with the network rule maker hinting at a key rule change as early as next week.

In a strong sign that the country’s energy market rule-makers and regulators are finally trying to catch up with the pace of technology, the Australian Energy Market Commission flagged a likely rule change that puts it into virtual light-speed compared to the glacial process it had been renowned for.

In a statement published on Thursday, the AEMC said it planned to initiate a rule change “next week” aimed at streamlining the regulatory approval process for a $1.5 billion, 330kV link proposed for between Robertstown S.A. and Wagga Wagga in NSW.

The proposed rule change was submitted on Thursday by Energy Security Board chair Kerry Schott, following the Wednesday submission of a final report on the interconnector proposal – dubbed “EnergyConnect” – by its key proponents, transmission network companies ElectraNet and Transgrid.

While there is significant high-level support for the new interconnector – including from the Australian Energy Market Operator, which sees it as a crucial component of its Integrated System Plan – the proposal must now go through a complex and often slow regulatory test known as RIT-T (Regulatory Investment Test for Transmission).

To streamline this process, Dr Schott has proposed amending the National Electricity Rules to reduce the time between the completion of the RIT-T undertaken by ElectraNet, and the determination of the Australian Energy Regulator (AER) on whether ElectraNet can recover the cost of the project.

As AEMC explained on Thursday, the rule request would not remove any steps in the regulatory process, but instead save time by allowing the AER to get started on a cost recovery assessment at the same time as the assessment of whether the project is the best option for consumers.

By Schott’s reckoning, doing these two things as the same time could save up to six months on the RIT-T process, as longs as ElectraNet can provide the AER with all it needs “in a timely manner.”

“The AEMC plans to initiate this rule change next week. The changes proposed by Dr Schott are closely related to those being considered by the AEMC as part of the early implementation of ISP priority projects rule change,” the rule maker said on Thursday.

“The RIT-T dispute process, which must be completed before the AER can start its assessment, would remain unchanged. Under the dispute process, stakeholders have 30 days to lodge a dispute notice about a RIT-T if they have concerns about how a transmission business has applied the test or its cost-benefit calculations.”

Sophie Vorrath

Sophie is editor of Renew Economy and editor of its sister site, One Step Off The Grid . She is the co-host of the Solar Insiders Podcast. Sophie has been writing about clean energy for more than a decade.

Recent Posts

The direction of China’s coal journey is clear – the pace remains the question

There is something for everyone in China’s coal data, but the direction that the energy…

27 February 2026

Yes, Santos was cleared of greenwashing. But a climate law reckoning still looms

Santos beat greenwashing claims in court, and while the ruling exposes the limits of climate…

27 February 2026

Big solar and batteries lead march to the grid, but new plans for wind are piling up

A flurry of new solar and battery projects has appeared in AEMO's grid management system,…

27 February 2026

“I’m it!” Bob Brown puts hand up to lead new national environmental watchdog

One of Australia's fiercest defenders of nature and biodiversity has thrown his hat into the…

27 February 2026

Energy Insiders Podcast: China’s clean energy surge reshapes coal, oil and the grid

Lauri Myllyvirta, lead analyst at the Centre for Research on Energy and Clean Air, on…

27 February 2026

AER sets cost to customers of Basslink, as troubled interconnector transitions to regulated asset

As early works – and a legal challenge – get underway for Marinus Link, the…

27 February 2026