$53.8 million for Stanwell Power Station

PRESS RELEASE

$53.8 million will be invested for a series of major projects at Stanwell Power Station west of Rockhampton, over the next year.

Queensland Energy Minister Mark Bailey announced today the projects will include $24.3 million in spending on major overhauls and $14.4 million for a control system upgrade, along with some smaller projects.

Mr Bailey said this investment was another example of the Palaszczuk Government’s commitment to a robust and secure energy system, with the works providing an important boost to the Central Queensland economy.

“Two of the four Stanwell Power Station units will be overhauled in the next 12 months. An overhaul of Unit 3 will commence next week and Unit 4 is scheduled to begin in June 2018.”

“There are approximately 60 contract companies that provide services for the overhauls, and many of these are locally based,” Mr Bailey said.

“These companies will provide electrical services, cranes, hydraulic work, and high-pressure cleaning, providing benefits for the local economy this year and next year.”

“Local businesses will also be providing accommodation, catering and transport for workers while these projects progress.”

“We will continue to use public ownership to back in Queensland consumers by ensuring a secure supply of energy and putting downward pressure on prices.”

Member for Rockhampton Bill Byrne said of the $53.8 million allocated for major works at Stanwell Power Station, around $11 million will be injected into the local economy.

“Stanwell Power Station is one of the most efficient coal-fired power stations in Australia. Overhauls maintain the power station’s efficiency, which means coal use and emissions are maintained at minimum levels,” he said.

“The power station overhauls are large-scale engineering projects that maintain the reliability, efficiency and safety of electricity generation units.

“The control system at Stanwell Power Station controls and monitors the boiler, turbine generator and auxiliary plant and provides automatic protection functions to trip plant and generating units to minimise risk.

“The current control system is nearing the end of its operational life and it is anticipated the upgrade will extend its life by approximately 15 years.”

 

Media contact: Zoe Russell – 0428 079 640

Share
Tags: Governments

Recent Posts

Councils call for national climate compensation fund – and they want the polluters to pay

Local governments want a national fund to help pay for the soaring costs of climate…

19 June 2026

Burning forest “waste” to make cement is poor climate policy, poor environmental policy and bad economics

The Australian government has agreed to invest almost $53 million to help upgrade a coal-fired kiln to…

19 June 2026

Delaying clean energy is what really makes power bills soar

What is making us poorer is not the move to clean energy – it is…

19 June 2026

Energy Insiders Podcast: The problem with network tariffs

AEMC chair Anna Collyer discusses the pricing review, network tariffs, and the right of monopolies…

19 June 2026

“Great green incinerator:” Hanson channels Rinehart attacks on wind and solar, but it’s not all it seems

Gina Rinehart and her political protege Pauline Hanson launch new attack on wind and solar,…

19 June 2026

Big battery blitz: Six-hour giant with 4.8 GWh of storage approved as 8-hour project joins queue

One of the biggest isolated grids in the world continues to flex its energy storage…

19 June 2026