“1,000 tonnes of spinning metal:” Network inks deal to add four syncons to state grid

Published by

Queensland’s government-owned transmission giant Powerlink has signed a deal with Hitachi Energy for the supply and installation of four synchronous condensers that will strengthen the electricity transmission network in Central Queensland.

Powerlink and Hitachi on Tuesday announced the agreement to deliver “1,000 tonnes of spinning metal,” as part of larger effort by Powerlink to reinforce the Central Queensland network as part of the Queensland Energy Roadmap.

Hitachi Energy will design, integrate, install, and commission the balance of plant, while its technology partner Baker Hughes will supply the four, 265 tonne synchronous condensers, or “syncons”, each equipped with flywheels to manage 1,442 megawatts (MWs) in inertia.

Construction is expected to get underway in 2027 and installation of the synchronous condensers completed by the end of 2029.

Once operational, the four syncons will reinforce the Central Queensland network, maintaining voltage stability and inertia to ensure reliable grid operations.

Disturbingly, despite the widely publicised role of synchronous condensers in other states for providing extra renewable energy capacity, the Queensland government and Powerlink described the new syncons as complementing “system strength provided by existing coal generation in the market, along with other measures include grid-firming battery energy storage systems, gas turbines and pumped hydro energy systems.”

The nearly identical press releases published by the Queensland government and Powerlink both failed to indicate any future renewable energy capacity, saying only that the government’s current plans are centred around “[improving] Queensland’s existing energy assets while building what is needed for the future”.

“The Energy Roadmap is investing in coal and gas generation to safeguard domestic energy security and support industry across the State, while building the capacity needed for the future,” the press releases added.

Two of the new synchronous condensers will be built at Calliope River Substation near Gladstone, with one each at Nebo and Stanwell substations by 2029. 

“These machines will ensure the core of Queensland’s power system remains strong,” said Darryl Rowell, Powerlink interim chief executive.  

“The first two of these machines will become operational in early 2029, with the following two operational later that year. 

“Our team has been out across Central Queensland talking about the need for synchronous condensers and is engaging with communities about the specifics of the project, including the locations of the machines.” 

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Joshua S Hill

Joshua S. Hill is a Melbourne-based journalist who has been writing about climate change, clean technology, and electric vehicles for over 15 years. He has been reporting on electric vehicles and clean technologies for Renew Economy and The Driven since 2012. His preferred mode of transport is his feet.

Share
Published by

Recent Posts

Solar and wind remain “backbone” of least-cost future grid, as batteries squeeze gas to a fraction of the mix

Firmed solar and wind still lowest-cost pathway for Australia to reach net zero emissions, new…

15 July 2026

Hunter Valley collieries to be greened-up as clean industrial hubs in “post mining land transformation”

State and federal governments aim for 7,000 green and industrial jobs under new master plans…

14 July 2026

“We cannot wait:” Changes made to renewable tenders to ensure wind and solar projects actually get built

Key changes have been made to renewable tenders to ensure that the winning projects can…

14 July 2026

Coal closure delays and soaring prices mean more batteries and fewer syncons to keep heartbeat of grid

Soaring syncon costs and supply issues, along with delays to coal closures, is opening up…

14 July 2026

Spitting chips: A deep dive into the data and token industry, and who carries the GPU risk

This note provides an estimate of demand and supply of tokens, draws a conclusion about…

14 July 2026

Wind project with an 8-hour battery hybrid looks for final green light after speeding through state approvals

A new wind-battery hybrid project speeded through state approvals, now it needs one more nod,…

14 July 2026