Power bills would rocket by hundreds of dollars per household if 5 gigawatts (GW) of data centres connect to the existing east coast grid without bringing any new generation with them, a new study says.
The new analysis of what the final bill might look like if data centres are allowed to “build first, catch up later”, as was one recommendation by the Australian Energy Market Commission (AEMC), suggests the cost to consumers will be very high.
If the 5 GW “test scenario” plays out, that load alone would cause wholesale power prices to rise by $40 billion across Queensland, New South Wales (NSW), Victoria and South Australia between 2029 and 2035.
The costs of that lag must be carried by data centres, the Smart Energy Council (SEC) says in a new report called $40 billion hike.
Most of this sum – some $37 billion – will be paid by everyone else in their power bills, as the extra demand allowed more expensive gas power to fill demand gaps while renewable generation plays catch up.
Some in the renewable energy sector are salivating over the prospect of data centres being the anchor buyers needed to reach a final investment decision, and a driver of higher wholesale prices to be commercially viable.
But the sector has also rapidly become a bête noir for communities threatened by their massive water and energy needs, and what the consequences of that will be for everyone else.
“The [5 GW] scenario… shows what a lag between demand and supply costs other customers,” says the SEC analysis.
“The Clean Energy Finance Corporation (CEFC) and Baringa found that without matching new supply, New South Wales’ wholesale prices would be 26 per cent higher in 2035, and 3 per cent higher where renewables and storage are added alongside the load.”
Queensland is the hardest hit under the SEC’s 5 GW scenario because of its plan to financially support new gas and coal stations to power the state, and possibly data centres as well.

“Australians suffering through a cost-of-living crisis can’t be expected to foot the bill for tech companies and artificial intelligence infrastructure.
“Carve-outs and special passes to rely on coal-fired generation, such as the Crisafulli government’s coal-fired computing ambitions in Queensland, would carry immense costs for consumers and the public purse,” SEC chief David McElrea said in a statement.
A new coal power station built for a single data centre could cost taxpayers between $15-20 billion, according to an analysis by Green Energy Markets.
Legislation is coming
Prime minister Anthony Albanese promised to make BYO renewables a legal obligation for data centres, but later caved and promised carve outs for states that want to use gas to power the new sector.
Queensland premier David Crisafulli promptly assumed that it would also include coal, saying he wants a new coal-fired generator to power the Western Downs region.
On Monday, industry minister Tim Ayres told a Senate Estimates hearing the government will introduce the legislation “shortly”.
“This legislation will use national rules to make sure that those investments don’t push up the price of electricity, which is what has happened in other jurisdictions,” he said today.
“A lack of kind of planning and a regulatory framework has meant that there’s more customers for the same amount of electricity generation and transmission infrastructure.
“So number one, lower costs. That’s what it’s designed to do. Number two. Ensure that data centres procure new renewable generation, adequate firming demand flexibility in terms of their own operations.”
The SEC warns this legislation will decide who pays the long term costs of the data centre boom, particularly given carve outs for Queensland to use gas will have flow on power price effects to the rest of the National Energy Market.
It wants to see a strong BYO renewables mandate and binding connection conditions that makes the data centre rather than other customers carry the cost of any lag.
There is already an overwhelming number of data centre proposals for Australia: At the end of June, AEMO had 17 data centre projects in its connection queue with 9 GW of capacity, of which five (1.4 GW) were being implemented.
The SEC calls its 5 GW threshold a “credible stress test scenario” because of what the Australian Energy Market Operator (AEMO) already has in its queue and announcements that followed.
That figure doesn’t include massive projects such as the 2.16 GW Zerra facility in Queensland or Quinbrook’s 800 MW Supernode.
But there are two saving graces for worried consumers and industry bodies: According to the Carbon Zero Initiative, data centres seem to reserve twice the capacity in their connection requests as they actually use.
And the data centre industry is beginning to find out that connecting to a hard pressed grid isn’t quick and easy.
Western Sydney is now effectively closed for business as Transgrid says there is no room left for new data centres to connect.
In Melbourne, NextDC’s struggles and delays in getting enough grid capacity to its M3 data centre in Footscray has spelled the end for chairman Douglas Flynn and forced CEO Craig Scroggie to forfeit millions of dollars in future bonuses.