Coal

Callide coal generator was being operated without approval when it blew up in 2021

Published by

The Callide C coal generator in Queensland was being operated without the required regulatory approval when one of its units blew up in May, 2021, and nearly crashed the grid.

The Australian Energy Regulator said on Wednesday that the owner of Callide, the state-owned utility CS Energy, has paid a $67,800 fine for an alleged breach of the National Electricity Law.

The AER says the fine relates to operating a generating system without the required regulatory approval, and it was discovered in its investigations into the events at Callide C, which caused multiple trips of generators and transmission lines on May 25, after what the AER delicately describes as a “plant issue.”

“This alleged breach is distinct from the AER’s ongoing investigation into the events that led to the 25 May 2021 power system event,” the AER said.

“Any entity that owns, controls or operates an electricity generator must apply to the Australian Energy Market Operator (AEMO) to be a Registered Participant for the activity or for an exemption from registration.”

The AER says Callide C was not a Registered Participant, nor did it have an exemption at the time of the explosion, and it turns out that had been the case for a number of years. The AER says an application was only submitted following its investigation, and one was finally obtained last month.

The fine equates to less than one hour’s revenue from the Callide C generator at full capacity (840MW), and based on the average price of wholesale electricity over the past year ($109/MWh), but the AER said it was an important issue.

“Failure to obtain the appropriate registration and exemptions can impede AEMO’s ability to track changes in the control or operation of a generating system,” AER board member Justin Oliver said in a statement.

“This reduced visibility could cause operational issues for AEMO including its ability to contact the appropriate staff that are responsible for the operation of generating systems to raise important matters including compliance issues and activities.”

The AER says it is continuing its investigations into the May 25 incident. AEMO and CS Energy have been approached for comment.

The two Callide C units are now not due to return to service until 2024, with the C4 unit – which suffered the dramatic explosion – delayed until May and July. The C3 unit, which also had to be taken offline to due to problems in the cooling towers, is expected back on line in February, 2024.

Update: In a statement, CS Energy blamed an “historian oversight” on its failure to obtain an exemption as required.

“Due to an apparent historical oversight, CS Energy did not hold the required exemption from registration as the operator of Callide C,” CEO Darren Busine said.

“We acted promptly to seek the required exemption as soon as the oversight was brought to our attention. We are unaware of any impact caused to consumers or other market participants as a consequence of us not holding the relevant exemption.”

CS Energy owns Callide C in a joint venture (JV) with IG Power and operates Callide C on behalf of the JV. Callide Power Trading (CPT) is the registered market participant for Callide C and trades the output of the Callide C generating units in the market on behalf of the JV.

Generating units cannot have more than one Registered Participant, and CS Energy (as the operator of Callide C) was required to hold an exemption from registration.

Giles Parkinson

Giles Parkinson is founder and editor of Renew Economy, and of its sister sites One Step Off The Grid and the EV-focused The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share
Published by

Recent Posts

CSIRO hails successful road test of lower-cost green hydrogen technology at steel plant

CSIRO says its innovative, potentially lower cost green hydrogen technology has completed 1,000 hours of…

1 December 2024

Eyes of the energy world on Australian vanadium battery tech

Long duration vanadium storage technology being trialled in Kununurra, it could be rolled out across…

1 December 2024

Energy Insiders Podcast: Getting the best out of the grid

Energy expert Gabrielle Kuiper on getting the best out of distributed energy resources in the…

29 November 2024

Australian homes could slash energy bills by two thirds by cutting out gas and petrol, AEMC says

Australian households could lower their bills by over two thirds if they fully electrify their…

29 November 2024

In the end, the only blackouts were in the media headlines: But there has to be a better way to do this

Updated: Blackout featured prominently in media headlines this week, but not on the grid. But…

29 November 2024

Trina submits approval for Victoria big battery, as locals campaign against solar and storage projects

Trinasolar and Mint Renewables have now both lodged planning applications for neighbouring big batteries in…

29 November 2024